Project Charter Final
Date: May 8, 2015

Project Charter

Purpose of Project Charter

Bausch & Lomb Inc. (B&L) is well known for its world-class delivery in eye care products. From their innovative creations of lenses, pharmaceuticals, and ophthalmic surgical products, Bausch & Lomb truly lives up to its mission of being “number one in the eyes of the world” every day. In addition to eye care products, the company began to invest in related external businesses to increase their profits and brand. In order to make sure these projects were being implemented correctly and running efficiently, B&L started to focus significantly on project management. At first, the company had a rough start with a project completion rate of less than 50 percent (APQC, 2004, p. 44). However, with a heavier focus in project management implementations in the company, they increased significantly to average around 86 percent.

To continue the success of project delivery at Bausch & Lomb Inc., the company needs to perfect its greatest challenge in measuring project delivery and end results. Specifically, B&L has struggled with documenting the correct inputs that are critical to the project delivery process. Important parts of the organization, such as goal definition, timelines, and forecasting, are being incorrectly entered or not inputted in a timely manner, causing the project to lose its efficiency.

The purpose of the project charter is to improve Bausch & Lomb’s project delivery and end results by conducting a six-month trial period where all project related employees are required to submit their project documentation to management each week. Weekly, managers have to review the documentation and report their progress to the project director. The project director would document and measure the reporting and confirm that project timelines have the correct goals, definition, timelines, and forecasting within Microsoft Project and are updated each time they are sent. At the end of the six-month period,

You May Also Find These Documents Helpful

  • Better Essays

    Project Charter

    • 956 Words
    • 8 Pages

    The purpose of this project is to do a complete frame off restoration of a 1968 GMC Step Side Truck. Phoenix Rain Customs will be using the most advanced processes and technologies available to bring about the complete restoration of Lola. The goal of this project is to utilize and incorporate modern safety features and technologies while retaining the classic look of the vehicle.…

    • 956 Words
    • 8 Pages
    Better Essays
  • Satisfactory Essays

    Project Charter

    • 531 Words
    • 3 Pages

    Owner(Manufacturing of composite hockey sticks and thermoset molded parts for defense, energy and transportation sectors)…

    • 531 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Course Project Charter

    • 567 Words
    • 3 Pages

    | The Purpose: The construction of a new plant in Huntsville, Alabama for the SEITZ Corporation to be operational by June 30, 2012…

    • 567 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Project Charter

    • 592 Words
    • 4 Pages

    The current data network is 10 years old, EoL and out of warranty. We can still maintain the network with a premium service package, but the cost is 4 times what last year’s maintenance cost was. Our plan is to replace the network over a 2 year period. This refresh will meet goals of the company by Improving services, helping achieve the 5x9s initiative that was put out last year, and reduce cost over the life of the new solution.…

    • 592 Words
    • 4 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Project Charter

    • 640 Words
    • 3 Pages

    1. A condition or capability is needed by a user to solve the problem or archive an objective.…

    • 640 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Project management can be described in a multitude of ways and is used in a wide variety of industries. The projects themselves can be small and simple or on large scale and extremely complex. No matter the size of the project if they are knowledgeable and precise in the planning it will ultimately start, execute, and close with success. [1] A project is a temporary endeavor undertaken to create a unique product, service, or result. The project being written about today was not on a large scale but overall made a large impact in the company atmosphere.…

    • 692 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    Project Charter

    • 792 Words
    • 7 Pages

    Orange Creek, Inc. is implementing a network infrastructure for their banking software. A new building has been constructed to provide on-site IT staff, management and administration office space. The employees will be dedicated in designing, developing, and testing banking software at the location in Lexington, Tn.…

    • 792 Words
    • 7 Pages
    Satisfactory Essays
  • Good Essays

    Week four’s focus on the project execution process was beneficial. I was not as familiar with the procurement management process as I am with quality, risk, and communication management. This week I was most comfortable with communication management and the tools and techniques for distributing formal communication. Communication management is something I have to do daily to ensure my department has the information necessary to meet goals, which is similar for the information required of a project team. I also felt comfortable with the risk management plan and recently have been participating in a project to review all process and procedures of our service teams. The focus of this project is to identify a standard process but also identify the risks of…

    • 755 Words
    • 4 Pages
    Good Essays
  • Good Essays

    Project Charter

    • 682 Words
    • 3 Pages

    2. All information regarding the members is captured and these informations are stored in a single record book with no back up data as the cashier said. They rely heavily on that record book for the…

    • 682 Words
    • 3 Pages
    Good Essays
  • Best Essays

    CIS 517: Project Management

    • 2741 Words
    • 11 Pages

    Project charter is necessary for the initiation of the project. It is defined as a signed document which is formally defined and authorizes the project. This document is considered an agreement of the project which includes the scope of the project, its objective and the constraints; it can be a difficult but is considered healthy for the group of the key stockholders. Without a project charter it becomes very hard to achieve the goals of the project.…

    • 2741 Words
    • 11 Pages
    Best Essays
  • Satisfactory Essays

    Door To Doc Case Study

    • 833 Words
    • 4 Pages

    The project charter established a focus and direction for the team, and also established parameters for the process beginning and completion. The team developed a process map of the current process. Employees working in the process assisted in verifying the map details.…

    • 833 Words
    • 4 Pages
    Satisfactory Essays
  • Good Essays

    Amiodarone Project

    • 506 Words
    • 3 Pages

    According to Harding (2014), the project charter is a critical document between the project manager and…

    • 506 Words
    • 3 Pages
    Good Essays
  • Better Essays

    The Work Breakdown Structure (WBS) contains the different activities within a project. Every activity necessitates outputs from several experts following different measures and timelines. The total of these activities represent the end deliverable. In order to control the task effectively the project supervisor must track the logical order of the various parts. He must visualize the final project deliverable. Views regarding project management, benefits and restrictions, bottlenecks, changes to risk or time in a crisis, and four points touched.…

    • 1092 Words
    • 5 Pages
    Better Essays
  • Powerful Essays

    Project Management

    • 689 Words
    • 3 Pages

    Project indirect cost represents overhead cost. Indirect cost varies directly in time. For instance, if our daily overhead cost is 250 euro, any reduction in project duration has to represent a saving of 250 euro per day. Project direct cost is clearly charged to a specific work package such as labor, materials and equipments. In order to create a cost-duration graph we have to apply three major steps:…

    • 689 Words
    • 3 Pages
    Powerful Essays
  • Better Essays

    1. Please use a document header that includes: your name, id number, the page number, and total number of pages (i.e. page # of #) on every page…

    • 1900 Words
    • 6 Pages
    Better Essays

Related Topics