Preview

Simulation of Breakwater Construction

Satisfactory Essays
Open Document
Open Document
351 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Simulation of Breakwater Construction
Introduction
Construction of breakwater involves wide range of activities that need transportation of resources from wide range of sources. Moreover, since most of the materials required for construction have to be carried to the site of construction by ships and barges, it will not be economical to transport materials as and when required as in land constructions. So it is necessary to plan activities in a way that would minimize the number of cycles required for barges, which further are limited by their carrying capacity and availability.
At the same time, the duration required for project completion gets increased if the number of barges used are reduced, which further may increase overhead costs and liquidated damages, if applicable. Also there are many other technical and construction issues which influence the cost of construction. It would be beneficial from a project’s perspective to optimize the time and cost of the total project so that it finally benefits the profitability and efficiency of the project.
Objective and scope
The main objective of this project is to apply simulation in optimizing the cycle time and logistics of various activities involved in construction of a breakwater. The main benefit of this simulation analysis is a detailed look at the techniques for improving breakwater construction
The scope of this project is limited to breakwater construction sites. The project scope includes modeling, simulation and optimization of construction methods used in breakwater
Methodology
In this project suitable simulation techniques are used to model the construction of a breakwater and capture the uncertainties in the construction methods. Optimization is done with the help of software like EZstrobe which use Monte Carlo simulation to simulate the activities and suggest improvements. Application of Heuristic methods and Genetic algorithm to arrive at improvements is suggested.

Data and facilities required
• Productivity, Cycle time,

You May Also Find These Documents Helpful

  • Good Essays

    Mr Sean

    • 2500 Words
    • 10 Pages

    Once the flow rate of the river is determined we can begin hydraulic analysis on the bridge. The cross sectional area of the river and the soffit level are other factors required when working out the hydraulic analysis. The soffit is the under surface of the bridge superstructure, it has to be a required height in relation with the Roads and Traffic Authority (RTA) NSW. In a 100 year event there has to be an allowance of 300mm gap from the top of the water level to the lowest part of the bridge deck. The hydraulic analysis will look at the forces on the bridge piers as a result of debris crashing into them and the forces of the water. The foundations of the piers will also be investigated for local scouring. The bridge will be designed in relation to the Australian Standards and the…

    • 2500 Words
    • 10 Pages
    Good Essays
  • Good Essays

    Sci 275 Bridger Tetons

    • 891 Words
    • 4 Pages

    proposed well pads and road networks that would have to be put ni place, summer habitats and…

    • 891 Words
    • 4 Pages
    Good Essays
  • Good Essays

    Enb110 project report

    • 5848 Words
    • 20 Pages

    Boon, G. (2008). 5 Steps to Building a Model Bridge [EBL version]. Retrieved from www.garrettsbridges.com…

    • 5848 Words
    • 20 Pages
    Good Essays
  • Good Essays

    Justin Taglianetti and I decided to construct a simulation of the Sydney Harbor Bridge located in Sydney, Australia. Our bridge, opened in 1923, is a steel arch bridge that is connected at the helm by two towers. It has hinges on both ends to allow for expansion and contraction of the steel during times of heat and cold. This prevents the bridge from collapsing in on itself and permits the eighteen centimeters of size change during a normal day. On our bridge model, we changed the idea of it being held up by these two towers and constructed a set of three legs in order to attain the support it needed to hold up. Justin and I also felt we needed trusses as well as a tongue and groove modification to contribute to the support of the bridge by…

    • 1198 Words
    • 5 Pages
    Good Essays
  • Good Essays

    The purpose of accelerated bridge construction is to ensure the project planning, procurement, and logistics approach are modified to ensure tasks with long lead times, traditionally completed onsite, are of highest priority and completed using creative solutions. Multiple scenarios require the need for accelerated bridge construction technologies; where a bridge is being constructed or reconstructed over an existing roadway in use, where a bridge is being reconstructed or replaced for an existing roadway currently in use. Accelerated bridge construction technologies aid in the construction of the required infrastructure while minimizing or limiting the distribution of traffic. Where the impact upon traffic is a concern, relocation of roadway…

    • 400 Words
    • 2 Pages
    Good Essays
  • Powerful Essays

    In the following three sections, a summary of the engineering science used to find a solution to the project will be presented. These sections have been nominated by Sunshine Water Pty Ltd as per the Client Brief.…

    • 2213 Words
    • 9 Pages
    Powerful Essays
  • Powerful Essays

    Our analysis of the proposal for the construction of a new 180,000 DWT vessel has brought us to the conclusion that the project should not be undertaken. Our recommendation and decision is based on a discounted cash flow analysis of expected future cash flows from the vessel that produced a net loss for the project of $7,201,639. Included in this recommendation are a number of important assumptions, each of which is described in detail below, that we believe are neither conservative nor aggressive in nature. A sensitivity analysis of major assumptions in our analysis is included on the final page of this memo. In each viable case, we arrived at the same conclusion to not undertake this project.…

    • 1467 Words
    • 6 Pages
    Powerful Essays
  • Satisfactory Essays

    Mb300 Unit 1

    • 4739 Words
    • 19 Pages

    Welcome to the unit on Operations Research Management. Operations Research Management focuses on the mathematical scoring of consequences of a…

    • 4739 Words
    • 19 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Confederated Pulp & Paper

    • 554 Words
    • 3 Pages

    Objective: Optimize pile size to minimize costs associated with providing wood, given that the number of days the river is frozen is random.…

    • 554 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Great Lakes

    • 710 Words
    • 3 Pages

    2 When considering entrance into the new market, there are several initial and long term costs that should be explored. Because the current vessels cannot be converted to container vessels, an additional fleet will be necessary. In addition to the vessels and cranes, other equipment may need to be added to the company’s inventory. Some fixed costs on the waterways associated with the new vessels may increase due to the size and function of these new vessels. Labor rates and contracts may also change with the nature of the new business. Variable cost is also a factor when considering new bulk materials that involve, for example, the transportation of hazardous materials and containment.…

    • 710 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    References: ASCE (American Society of Civil Engineers). (2005). Report Card for America 's Infrastructure (on-line). Available: http://www.asce.org/reportcard/2005/index.cfm.…

    • 1860 Words
    • 8 Pages
    Powerful Essays
  • Satisfactory Essays

    Fong, Patrick S. W. Kwok, Cecilia W. C., Journal of Construction Engineering & Management; Dec2005, Vol. 135 Issue 12, p1348-1356, 9p, 7 charts, 1 diagram, 1 graph. Retrieved December 5, 2009.…

    • 640 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    PESTEL Analysis

    • 491 Words
    • 5 Pages

    Creating of free-trade zones near new shipyards for cost cutting in ships construction (order of foreign material and equipment)…

    • 491 Words
    • 5 Pages
    Satisfactory Essays
  • Good Essays

    The PMBOK framework is applied for this case. It covers the design, execution and evaluation phase. The case does not give any details pertaining to the finishing phase. Also no details are given about the environmental and managerial aspects of the phases mentioned in the case.…

    • 985 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    Chief

    • 2199 Words
    • 9 Pages

    Level: 3 Assignment Code: SIM335 Issue date: 12 November 2012 Contribution to module assessment: 100% dition, a This is an individual assignment - complete both tasks 1 and 2 Background: The assignment is intended to bring out the benefits and limitations of different approaches to project planning and control by relating these to the circumstances in the cases outlined. It is also intended to allow students to demonstrate their learning and competence in respect of the management of resources generally, but in particular elements of scope, schedule, quality, and cost. Case 1: Mangeist Ltd is an organisation which provides plant and materials to the building sector. These products include: Cement Mixers, Dump Trucks, Compressors and Pneumatic Drills, Lighting rigs, and Vibrating Plates. As part of your job as the Mangeist Ltd special projects manager, you have produced a list of activities that need to be addressed to source a new range of industrial forklift trucks for supply to the sector. The details are shown in the table provided. Please note: You must use the methodology detailed above table 1 headed “essential methodology”. Task 1 (40% marks) 1) Draw the network diagram (use activity on the node). (8 marks) 2) Explain how you determined the timing of activities and the total float. (6 marks) 3) Explain how you determined the project duration and the critical path. (6 marks) 4) If the project starts on the Monday 7 January 2013, what is the earliest date it can be completed using a 5 day working week? Assume no other holidays (explain how you calculated the figure). (4 marks) 5) If the following happened what would be the effect on the duration of the whole project? Explain the reasons. (6 marks) a) Activity B is delayed 1 day. b) Activity P is delayed 1 day. c) Activity 0 is delayed 2 days 6) Explain the limitations of Network diagrams. (10 marks) Module: SIM335 Managing Projects Module Leader: Michael Cassop-Thompson Return…

    • 2199 Words
    • 9 Pages
    Satisfactory Essays