Project Close Out
CDC UNIFIED PROCESS
PRACTICES GUIDE
PROJECT CLOSE-OUT
Purpose
The purpose of this document is to provide guidance on the practice called Project Close-Out and to describe the practice overview, requirements, best practices, activities, and key terms related to these requirements. In addition, templates relevant to this practice are provided at the end of this guide.

Practice Overview
The practice of project close-out finalizes all project activities completed across all phases of the project to formally close the project and transfer the completed or cancelled project as appropriate. The purpose of project closeout is to assess the project, ensure completion, and derive any lessons learned and best practices to be applied to future projects. However, in multi-phase projects, the close-out practice may be applied at various stages of the project; upon deliverable completion, upon phase completion, upon iteration completion, at designated times during the project’s life, or at whatever other juncture represents a completed segment of project work. Applying the close-out practice in this manner closes out only the portion of the project scope and associated activities applicable to that portion of the project.
The practice of project close-out consists of two main activity groups:
Administrative Closure – The administrative closure process defines activities, interactions, and related roles and responsibilities of the project team members and other stakeholders involved in executing the administrative closure procedure for the projects.
Performing the administrative closure process includes integrated activities to collect project records, analyze project success or failure, gather lessons learned, transfer the project products or services to production and/or operations, and archive project information for future use by the organization. Among other activities administrative closure includes:
• Confirming the project has met all sponsor,

You May Also Find These Documents Helpful

  • Satisfactory Essays

    CMGT 410 week 5

    • 308 Words
    • 2 Pages

    Once the review has been analyzed, it enables the project to officially come to a close.…

    • 308 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    PMBOKV4 ITTO 42 Processes

    • 1835 Words
    • 46 Pages

    ©2009 PMServicesNW. All rights Reserved. Page 1 of 9 Project Management Process…

    • 1835 Words
    • 46 Pages
    Satisfactory Essays
  • Good Essays

    Defines all the work required to complete a project successfully, and should ensure that the…

    • 1016 Words
    • 5 Pages
    Good Essays
  • Satisfactory Essays

    WK2D1 Unit 1 Assignment

    • 691 Words
    • 3 Pages

    * Closing processes finalize all activities across all process groups to formally close the project phase. Examples of closing processes are archiving project files, closing contracts, documenting lessons learned and receiving acknowledgement of project completion.…

    • 691 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    The scope of the project will need an outline so the work which needs to be performed is available. Prioritizing, budgets and timelines are in this phase as well.…

    • 447 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Project management can be described in a multitude of ways and is used in a wide variety of industries. The projects themselves can be small and simple or on large scale and extremely complex. No matter the size of the project if they are knowledgeable and precise in the planning it will ultimately start, execute, and close with success. [1] A project is a temporary endeavor undertaken to create a unique product, service, or result. The project being written about today was not on a large scale but overall made a large impact in the company atmosphere.…

    • 692 Words
    • 3 Pages
    Good Essays
  • Good Essays

    Week four’s focus on the project execution process was beneficial. I was not as familiar with the procurement management process as I am with quality, risk, and communication management. This week I was most comfortable with communication management and the tools and techniques for distributing formal communication. Communication management is something I have to do daily to ensure my department has the information necessary to meet goals, which is similar for the information required of a project team. I also felt comfortable with the risk management plan and recently have been participating in a project to review all process and procedures of our service teams. The focus of this project is to identify a standard process but also identify the risks of…

    • 755 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    This is a consolidated source of information which lays the foundation for successful completion of any project by identifying your project vision and communicating the overall approach for a project to all key stakeholder audiences.…

    • 322 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    Close Out Requirements

    • 2039 Words
    • 9 Pages

    The major activities in the Closeout Phase are shown in the diagram below, (Figure 1.1) consist of tasks that are typically administrative and logistical in nature. Initially, the focus is on performing the tasks associated with dispensing and reconciling personnel, property, and funding. When these tasks are finished, the attention of the project manager is focused on documentation of lessons learned and project closure. At some predetermined point, a Post Implementation Review of the project deliverables is conducted. The primary documents prepared during this phase include the Project Transition Checklist, Project Closeout Report, and Post Implementation Report.…

    • 2039 Words
    • 9 Pages
    Powerful Essays
  • Better Essays

    The Work Breakdown Structure (WBS) contains the different activities within a project. Every activity necessitates outputs from several experts following different measures and timelines. The total of these activities represent the end deliverable. In order to control the task effectively the project supervisor must track the logical order of the various parts. He must visualize the final project deliverable. Views regarding project management, benefits and restrictions, bottlenecks, changes to risk or time in a crisis, and four points touched.…

    • 1092 Words
    • 5 Pages
    Better Essays
  • Satisfactory Essays

    Project Closure Checklist

    • 522 Words
    • 3 Pages

    Project Retrospectives: Advocates of retrospective methodology claim there are distinguishing characteristics that increase its value over past lessons learned methods. What are they? How does each characteristic enhance project closure and review?…

    • 522 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    then team moves to new project. All the projects go through following three activity sets…

    • 912 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    114292

    • 5464 Words
    • 32 Pages

    9) The project closeout step requires project managers to consider the types of records and reports they and their clients will require at the completion of a project.…

    • 5464 Words
    • 32 Pages
    Satisfactory Essays
  • Satisfactory Essays

    The importance of performing close out activities before closing the project and the business risks associated with skipping these activities…

    • 823 Words
    • 4 Pages
    Satisfactory Essays
  • Satisfactory Essays

    PMP Exam Sample Questions

    • 9464 Words
    • 38 Pages

    (4) During the schedule development process the Project Manager may have to go through several iterations of the schedule before establishing the schedule baseline. All of the following are tools and techniques that may be used during this process:…

    • 9464 Words
    • 38 Pages
    Satisfactory Essays