Ms Project
Objectives - MS Project 2010

* Change the task type settings to control how resources affect task assignments * Apply a preset resource contour to change work value distribution * Working with task information forms

When planning a project schedule, adjustments are often needed to reflect necessary changes in project scope, assignments, etc. In MS Project, when an assignment is changed, the schedule is recalculated to display the changes. You can work with the scheduling method and the task type settings when making changes to the initial resource assignment.

In the previous lesson, the initial resource assignments were made for our project. But we need to learn how to make adjustments to how those resources are used. It is important that you read every part of this lab carefully, if not twice.

Working with Effort-Driven Scheduling

How a task reacts to the addition and removal of resources is defined by the scheduling method and the task type settings. In MS Project, the default scheduling method is effort-driven scheduling. Effort-driven scheduling extends or shortens the duration of a task to accommodate changes to resources but doesn't change the total work for the task.

Work is the amount of effort, or number of hours, resources put into a task.

The total work for a task is determined by the duration estimate for the task and the initial resource assignment using the following formula:

Work = Duration * Units

For example, say you give a task the duration of one day (or eight hours based upon a normal working day). If the initial resource assignment is two units (200%) of a particular resource, the total work for the task will be 16 hours.

16 hours = 1 Day (8 hours) * 200%

As resources are added or removed after the initial assignment, the amount of work is not recalculated, but redistributed among the resources. In other words, the duration is recalculated, not the work:

Duration = Work / Units

You May Also Find These Documents Helpful

  • Satisfactory Essays

    After fetching all the information, the actual allocation algorithm is performed here. Finally the allocated tasks are send to the corresponding resources.…

    • 464 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    Whatever the type of project, there are three important elements of cost, schedule and performance project managers must achieve in order to attain a successful project outcome. These elements are interrelated which means a slight change of one of the elements such as prolonging the project time schedule highly affect the element of cost or more…

    • 1428 Words
    • 6 Pages
    Powerful Essays
  • Powerful Essays

    In Chapter 5 (and handout), you learned about scheduling your projects. You will now apply these lessons to your project. Starting with the Microsoft Project Schedule that you modified to include your list of deliverables, you will want to:…

    • 2212 Words
    • 9 Pages
    Powerful Essays
  • Good Essays

    Each Model will recognise the nature of academic work and cover the factors listed in 3.3 of the University's Work Allocation for Academic Employees Schedule, and include a mechanism for work allocation in accordance with the standards of reasonable work allocation in 3.2 of the University's Work Allocation for Academic Employees Schedule. The mechanism in each Divisional Model will set work allocations which reflect a fair average assessment of the time to perform the work to a professional…

    • 680 Words
    • 3 Pages
    Good Essays
  • Good Essays

    HBP Simulation

    • 1046 Words
    • 5 Pages

    The number of tasks completed per week (NTCW) is the basis of a project’s success. A critical determinant is the amount of resources per week invested into the project, defining project costs. Resources (and costs) are determined by:…

    • 1046 Words
    • 5 Pages
    Good Essays
  • Good Essays

    Medical Coding Workflow

    • 282 Words
    • 2 Pages

    Productivity figures will be calculated by dividing the output by the amount of time to complete the task.…

    • 282 Words
    • 2 Pages
    Good Essays
  • Satisfactory Essays

    The Gantt chat in the Microsoft project shows each activity and estimated duration as when it will be completed. The Gantt chat also reveals that the estimated completion time for the entire project will be July 6, 2012 which is one week after the projected date set by the board of directors which is June 30, 2012. This is clearly indicates that the project would not be completed on time as it was projected. In my opinion I think July 6, 2012 is not too far from the expected project completion date, therefore I would suggest the project manager to revise the schedule and reschedule.…

    • 611 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    If Larry and Kate divided to two tasks equally it would be based how many hours it each of them to complete each task times half and totaled.…

    • 743 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    Work must be allocated considering the experience of the employee, the expertise, the skills, the knowledge, and the workload. Has the employee done the particular task before or taken on similar ones?…

    • 3829 Words
    • 13 Pages
    Powerful Essays
  • Good Essays

    Codeing Scenarios

    • 848 Words
    • 4 Pages

    Work – relative level of time, skill training and intensity to provide a given service…

    • 848 Words
    • 4 Pages
    Good Essays
  • Good Essays

    Red Zuma Project

    • 402 Words
    • 2 Pages

    2. Once the resource leveling is completed, the over allocated resources decrease from 4 to 2. The over allocated problems are design engineer and industrial engineer, with the greatest total slack for detailed marketing plan decreasing. In the end the project task changes in the duration period after resources leveling.…

    • 402 Words
    • 2 Pages
    Good Essays
  • Powerful Essays

    Dragonfly case study

    • 1041 Words
    • 5 Pages

    1. The activities involved for the project schedule can be represented using Central Path Method (shown below) showing various interdependence and parallelism among activities.…

    • 1041 Words
    • 5 Pages
    Powerful Essays
  • Good Essays

    Microsoft Project is an excellent tool to use to plan the implementation of a system. This is generally the responsibility of the Project Manager and is done at the beginning of the project and signed off on by the key stakeholders in the…

    • 764 Words
    • 4 Pages
    Good Essays
  • Powerful Essays

    Chapter 11

    • 9115 Words
    • 52 Pages

    3) In order to estimate completion of a Gaussian distributed activity with a 90% or higher degree of confidence, the time may be overestimated by as much as 200%.…

    • 9115 Words
    • 52 Pages
    Powerful Essays
  • Good Essays

    Table 45 shows the relative error between the adjusted function point and the phased effort distribution ratio. The phased effort distribution approach is more accurate than the adjusted function point as shown in Figure 49.…

    • 1454 Words
    • 6 Pages
    Good Essays