Management in Architecture
Management in Architecture ARCH 403; Spring 2013 Final Assignment
Student Name: Fatih Ersin
Student ID: 0920049
Project name : TECHNICAL ASSISTANCE OF A CINEMA MULTIPLEX BUILDING

Project location : Kosevsko Brdo, Municipality of Centre, Sarajevo, BiH

Investor : Private sector investor/client

Project Budget : 2.3 million €

Project Duration : 4 months

Target Group : Students, Residents

Project Manager : Fatih Ersin

1. BACKGROUND INFORMATION
1.1. Project Description

Due to improvement of social life in Sarajevo ,the client wanted to attrack people by a cinema multiplex building including other facilites beside cinema. According to his desires the site was detected where the students usually are, to take their attention and to satisfy their needs. The required documentation and permits are going to be issued. The budget is 2.3 million € and the techincal assistance should be done by taking care of the budget and desires of the client.

2. POREJECT STAKEHOLDERS

Municipailty Since the client has not mentioned where the complex is going to be, a site was selected by our assistance and the codes and regulations of the site were taken from centre municipality of Sarajevo. They might give the permits we need, or forbid some things in our design.

Client Client wishes to have a complex although he doesn’t have any Picture in his mind. Hence we will picture the complex and he might agree or disagree with some assistance.

Project Team From architects to engineers, all the team members are working on the Project according to client’s desires. They should finish their responsibilities on time.

Residents/Students near by The site was selected in a location where the social life is not so active, but ready to be since there are some faculties. A lot of Student live there and also the local people need to spend some time near by. Hence this complex will effect them and their life.

3. PROJECT OBJECTIVES AND

You May Also Find These Documents Helpful

  • Satisfactory Essays

    Qm 240 Week 4 Checkpoint

    • 505 Words
    • 3 Pages

    Assignment statement A company RYAN-MAYSSA has decided to implement a computer centre composed of a file server, 12 client computers, a printer and a scanner. The computer centre is used to run MICROSOFT OFFICE on client server architecture through the Microsoft Windows for client/server. In addition, an antivirus software for client/sever is also acquired to protect data in the centre. In order to guarantee the efficient use of the system, the company made a contract with a well known training centre to train employees, and contracts also IT support for its software. The below table provides the cost for purchased items. Type of cost Network infrastructure Description and amount Network exchange and Modem=250 KD Cable for network=300 KD Network installation = 300 KD Hardware File server= 750 KD 12 personal computers= 12*350 KD= 4200 KD Printer= 150 KD Scanner= 100 KD…

    • 505 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Jim Brown

    • 770 Words
    • 4 Pages

    The reasons that we propose this are because that this is the method that will save the company the most time. Not only does it save the company time, but if the company were to ever fall into trouble with labor union strikes, this plan is guaranteed to be the most cost effective when facing with the steep penalties of not meeting the time limit. In addition if everything goes very smoothly the company will finish the project 8 weeks earlier than expected and save money on overhead expenses.…

    • 770 Words
    • 4 Pages
    Good Essays
  • Better Essays

    Each team member needs to bring a suggestion for a solution as well as verification that tasks that you are responsible for at this point have been completed. As a team we must provide honest and open estimates about what we are doing to complete this project. We may have to do some partial overlapping in the next few weeks, but we will get this project completed successfully and on time. Some partial overlapping should get the project back on track and help with the budget…

    • 914 Words
    • 4 Pages
    Better Essays
  • Good Essays

    Milagro Beanfield War

    • 864 Words
    • 4 Pages

    planning to build a brand new resort. The only only problem is the location of this development is right…

    • 864 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    I was asked to a assume that I am the project manager of a software company and the team that I lead is in charge of delivering and update to tax preparation software for the next tax season. The fact is that the developers are spread across the country and I need to provide a status of the operation to the sponsor. They will also be informed about the two most important risks and the ways to mitigate these risks. The report will end by concluding whether or not additional resources are needed.…

    • 503 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    Ways of planning work to meet agreed deadlines can be by communicating a clear deadline with the customer, have a clear outcome of what the…

    • 1226 Words
    • 5 Pages
    Powerful Essays
  • Good Essays

    Project Delays

    • 4262 Words
    • 18 Pages

    In a perfect world, all construction projects would finish on time, without changes or disruptions. Despite the common public perception that contractors cannot wait for the changes to start on a project because that is where they allegedly “make their money”, most contractors would prefer their projects to complete without changes. Changed work complicates a project, invites delays and increases the project cost — all things that make owners unhappy.…

    • 4262 Words
    • 18 Pages
    Good Essays
  • Satisfactory Essays

    A&D HIGH TECH

    • 263 Words
    • 2 Pages

    What is your opinion on the potential for the project to be completed on time?…

    • 263 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Most of the Consultant put aside the preparing payment work because the work itself is a very tedious work and requires a maximum attention, because it involves the Client’s money, therefore it is understandable that why most of the Consultant tend to postpone the job. According to Wa’el Alaghbari, Mohd. Razali A. Kadir, Azizah Salim, Ernawati (2007) “From the consultant’s side, the first component that seems to be the cause of delay in construction projects is ineffective or lack of supervision, followed by slowness in giving instructions and lack of consultant’s experience”. A survey carried out by Wa’el Alaghbari, Mohd. Razali A. Kadir, Azizah Salim and Ernawati proved that the ineffectiveness of Consultant was one of the reasons of delay in a construction project. We can see that the effectiveness of Consultant with their job also play an important role in delivering a successful project. Consultant need to change their attitude in work and be more productive especially when it comes to prepare payment for Contractor because they must be paid on time to deliver a quality work. Consultant need to understand the important of preparing payment to the Contractor and not classify the work as not important compare to other works. Give payment early can prevent the…

    • 1083 Words
    • 5 Pages
    Good Essays
  • Satisfactory Essays

    Pob Sba

    • 305 Words
    • 2 Pages

    On the property its self is a gaming arcade to help promote our products and the video-games we develop and by our company being in the city is a major part and a great advantage of advertisement over other companies. The business is in a suitable location because the public is what makes our business successful.…

    • 305 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    F&B Management Case Study

    • 1160 Words
    • 5 Pages

    This is a venue of a multi-functional hall that is ideal for meetings and social functions. It can be divided into two separate areas with a maximum capacity of one hundred guests per area. The Jocel’s Garden Venue fully air-conditioned and equipped with modern sound systems, retractable chairs and tables, food and catering services, and full-time venue staff. The venue is really built for a purpose, in a manner that the Jocel’s Garden Venue is applying for accreditation to the Department Of Tourism.…

    • 1160 Words
    • 5 Pages
    Powerful Essays
  • Powerful Essays

    The purpose of this study is to provide people the awareness of Shaikh Zayed’s Housing Project and to provide them right kind of information but just at the single place.…

    • 1810 Words
    • 8 Pages
    Powerful Essays
  • Good Essays

    Having been in India since June 2009-mostly in Bangalore- I have visited Mathru Blind School on numerous occasions. A number of these were impromptu visits. I have also visited the rented premises where Mathru is maintaining a hostel for college level blind students from outside Bangalore and interacted with the students. I have seen the site of the future building that Mathru will be constructing for a vocational training center, hostel for blind college students and later, a home for destitute blind women.…

    • 392 Words
    • 2 Pages
    Good Essays
  • Powerful Essays

    Surveying Report

    • 1603 Words
    • 7 Pages

    We initially began a desk study of the site. This involved looking into the site uses in order to gain valuable information about the area. We also looked at adjacent buildings (e.g. the Harbour Hotel) and roads connected to the car park. From this we could evaluate some important points such as:…

    • 1603 Words
    • 7 Pages
    Powerful Essays
  • Powerful Essays

    Sheraton Hotel Case Study

    • 2873 Words
    • 12 Pages

    Provide specifications for all computing hardware and software to be used during the project and for the hotel.…

    • 2873 Words
    • 12 Pages
    Powerful Essays