Preview

Project Delays

Good Essays
Open Document
Open Document
4262 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Project Delays
Contents

Project Delays, Disruptions, and Changes 2
TYPES OF PROJECT DELAYS 2
Delays fall into three general categories: 2
Excusable/Non-Compensable Delays 2
Compensable (Owner Caused) Delay 2
Non Excusable (Contractor Caused) Delay 3
DOCUMENTATION OF DELAYS, DISRUPTIONS AND CHANGES 3
The Current State of Washington Law Regarding Notice. 3
Proposed procedure and process 5
Proposed Legislation 6
DAMAGES FOR DELAY - New Developments 6
RCW 4.24.360 6
In the Scoccolo case 6
The City’s franchise agreement with Puget stated in part 7
The TCI franchise agreement 7
RESOLVING DISPUTES THROUGH MEDIATION AND ARBITRATION 7
Tips For Mediating Disputes 7
Arbitration 8
Dispute Resolution Using Project Controls 9
PROJECT CONTROL SYSTEMS 9
Cost Control Systems 9
Network Scheduling 10
Time impact analysis 10

Project Delays, Disruptions, and Changes

In a perfect world, all construction projects would finish on time, without changes or disruptions. Despite the common public perception that contractors cannot wait for the changes to start on a project because that is where they allegedly “make their money”, most contractors would prefer their projects to complete without changes. Changed work complicates a project, invites delays and increases the project cost — all things that make owners unhappy.

In reality, nearly all projects of any substantial size experience changes and/or delays, therefore the parties are well served by thinking about how they will handle changes and delays prior to the start of construction. Setting out a framework in the contract for dealing with this inevitability is in the interest of both the contractor and the owner.

TYPES OF PROJECT DELAYS

Delays fall into three general categories:

Excusable/Non-Compensable Delays.

In these situations neither party is responsible to the other for any costs associated with the delay. These delays are those that are typically included in force majeure clauses — abnormal

You May Also Find These Documents Helpful

  • Good Essays

    Jim Brown

    • 770 Words
    • 4 Pages

    From what we can determine so far the main issues revolving around your construction project are unionized workers starting strikes and weather concerns during December. We are also informed that the company will suffer from a $500 per week penalty fee on overhead expenses if the construction project is not finished on time. It is also stated in the contract that a penalty clause of $15,000 per week of delay beyond February 15 of the following year will be implemented.…

    • 770 Words
    • 4 Pages
    Good Essays
  • Powerful Essays

    It221 Final Project

    • 2390 Words
    • 10 Pages

    Currently Cyber Solutions has satellite locations in 15 major cities around the United States that provide onsite IT solutions for companies within their service area, but do not have an integrated database that updates…

    • 2390 Words
    • 10 Pages
    Powerful Essays
  • Satisfactory Essays

    “Very few projects are ever completed according to the original plan. The changes to the plan result from either increased knowledge, a need for competitiveness, or changing customer/consumer tastes. Once the changes are made, there is almost always an accompanying increase in the budget and/or elongation of the schedule.”(Kerzner, p.949, 2009).…

    • 317 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Three Selected Clauses

    • 984 Words
    • 4 Pages

    The liability of completing additional work requirements resulting from change order directives is shifted toward the subcontractor through the inclusion of a change order clause. This is applicable to the conditions stipulated within the change order clause stricken from the contract. The owner under this clause is given authority to freely issue work order directives with the consideration of the contractor. These changes potentially leave the subcontractor subjected to any actual damages suffered from persistent changes to contractual work obligations. The assumed work liability of the subcontractor is further enhanced by the ambiguous language used to outline the owner and contractor’s responsibilities when determining the acceptance of an issued change order directive. This can lead to an increase in vulnerability for a subcontractor who is bound to the changes made in an arbitrary decision making process. To mitigate the risk of change order directives, I recommend replacing the existing change order clause with a condition defining the parameters for substantial completion of work. The term substantial completion is often used to defend against claims made by the owner against a contractor accused of a breach in the contract. This term can also be utilized to defend…

    • 984 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    Termination for Cause

    • 324 Words
    • 2 Pages

    1) If the project has slipped into delays from which the contractor can make no reasonable recovery, and those delays significantly impact the project.…

    • 324 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Annotated Bibliography

    • 680 Words
    • 3 Pages

    Assaf, S.A. and Al-Hejji, S. (2006) Causes of delay in large construction projects. International Journal of Project Management, 24(4), 349-57.…

    • 680 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    and negotiating project conditions are common approaches to deal with the unexpected events. The discussion shed new light on one…

    • 5997 Words
    • 24 Pages
    Good Essays
  • Powerful Essays

    As it was often cited in class, no project can achieve success without proper coordination between three essentials: scope, schedule and cost. Change one, and the other two will be impacted. On the other hand, trying to prohibit all changes to a project is often fruitless and can have…

    • 1271 Words
    • 5 Pages
    Powerful Essays
  • Satisfactory Essays

    - By referring to the completed the job during the specific time will have a problem on delivering the crucial material to the construction site. A problem that occurs will cause a…

    • 929 Words
    • 4 Pages
    Satisfactory Essays
  • Good Essays

    Mid-India Construction Company (MICC) granted a refurbishing project at Director of National Institute of Management (NIM). The project should finish 8 months after contract award (Contract award: 17/11/12 Planned date for end of project: 27/06/13) before new academic term starts (01/07/13). MICC kicked off the project with one week delay on 24/11/12. One month after project commencement slow progress stresses both MICC and NIM project managers and casts the on-time project delivery on a shadow of doubt. MICC project manager realized the project resources are inadequate and unproductive. Meanwhile, NIM project manager insists that MICC should start different activity in parallel to compensate the delay of last month and mitigate the risk of overall project delay. MICC project manager has promised to NIM to increase resources and start parallel activities. Contractual penalty for major milestone delays has been explained in Exhibit 4.…

    • 726 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    the project can completely change, which would impact the ability for a firm to meet the required…

    • 279 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    collected list has 113 causes for delays which were categorized into 18 different groups. Most of…

    • 7276 Words
    • 30 Pages
    Powerful Essays
  • Powerful Essays

    Changes arise for various reasons and throughout all stages of a project. To regulate changes, a project manager must be aware of the causes and plan to avoid circumstances which give rise to changes. During the conceptual and development stages, numerous changes are made in the name of design development. At these primary stages the ability to influence cost is greatest and lest control is executed, the financial ability of the owner or the economic feasibility of the project may be surpassed.…

    • 1053 Words
    • 5 Pages
    Powerful Essays
  • Good Essays

    During the progression of works, the Contractor may encounter certain unforeseen difficulties and request for a needed time extension to revise the Completion Date for the works. The JCT Standard Building Contract With Quantities 2005 Edition (JCT SBC05) Revision 2 2009 will be used to determine the criteria for time extension and the various information…

    • 1825 Words
    • 8 Pages
    Good Essays
  • Powerful Essays

    Chapman, R. J. (1999), The Likelihood and Impact of Changes of Key Project Personnel on the Design Process, Construction Management and Economic 17:99-106.…

    • 18329 Words
    • 74 Pages
    Powerful Essays