Aib Homework Wk3 Problem 1 The following data were obtained from a project to create a new portable electronic. Activity Duration Predecessors A 5 Days --- B 6 Days --- C 8 Days --- D 4 Days A‚ B E 3 Days C F 5 Days D G 5 Days E‚ F H 9 Days D I 12 Days G Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) What is the Scheduled Completion of the Project? (2 points) 32 -> CORRECT b) What is the Critical Path of the Project
Premium Critical path method Project management
Problem 1 The following data were obtained from a project to create a new portable electronic. Activity Duration Predecessors A 5 Days --- B 6 Days --- C 8 Days --- D 4 Days A‚ B E 3 Days C F 5 Days D G 5 Days E‚ F H 9 Days D I 12 Days G Step 1: Construct a network diagram for the project. (NOTE: EF for activity H should be 19) Step 2: Answer the following questions: (15 points total) a) What is the Scheduled Completion of the Project? (5 points) Answer: 32 days b) What is
Premium Critical path method English-language films
Chapman might incur if the engagement is accepted. Another form that the partner in charge must complete is regarding information from predecessor auditors. All of this information is necessary in determining whether to take on this potential client. This form provides information about what a predecessor auditor’s evaluations where as well as seeing what the predecessor auditor’s
Premium Management United States Psychology
Smartphones for upper management Our company in order to save money will allow all employees to have a smartphone. We will be issuing these in priority order staring with the ten senior managers and then the one hundred employees who need an upgrade and then the fifteen new employees will receive one once their training is finished. The Scope of the Project The project scope for this project is the cost development‚ incorporation of companywide smartphones‚ and the deadline. The deadline for this
Premium Mobile phone Project management Management
Week Three Homework: AIB Problem PROJ586 Project Management Systems Problem 1 The following data were obtained from a project to create a new portable electronic. Activity Duration Predecessors A 5 Days --- B 6 Days --- C 8 Days --- D 4 Days A‚ B E 3 Days C F 5 Days D G 5 Days E‚ F H 9 Days D I 12 Days G Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) What is the Scheduled Completion of
Premium Critical path method Project management
The Sims 3 is the third major title in the life simulation video game developed by The Sims Studio and published by Electronic Arts. It is the sequel to the best-selling computer game‚ The Sims 2. It was first released on June 2‚ 2009 simultaneously for OS X and Microsoft Windows – both versions on the same disc. The Sims 3 was released to game consoles and smartphones on October 26‚ 2010‚ for PlayStation 3‚ Wii‚ Xbox 360‚ Android‚ iOS‚ and Nintendo DS. The Windows Phone version was made available
Premium
The Bestclean is a new cordless vacuum cleaner. An analysis of the task of building the Bestclean reveals the following list of relevant activities‚ their immediate predecessors‚ and their duration. Job Description Immediate Predecessors Normal Time(Weeks) A Product Design 6 B Market research Plan 2 C Manufacturing and engineering A 3 D Prototype A 5 E Marketing Brochure A 3 F Cost Estimate C 2 G Testing D 3 H Market survey B‚E 4 I Pricing and forecast H 2 J Final report F‚G‚I 2
Premium Project management Critical path method
hil61217_ch22.qxd 4/29/04 05:58 PM Page 22-1 22 C H A P T E R Project Management with PERT/CPM O ne of the most challenging jobs that any manager can take on is the management of a large-scale project that requires coordinating numerous activities throughout the organization. A myriad of details must be considered in planning how to coordinate all these activities‚ in developing a realistic schedule‚ and then in monitoring the progress of the project. Fortunately‚ two closely
Premium Project management Critical path method
Policy * Sacrilege; destroyed temples (Egypt and Babylon)‚ melted down the statue of Bel Marduk. * “Xerxes was a religious fanatic who deviated from the religious tolerance of his predecessors…he has become a paradigm for religious bigotry‚ fanatically interfering in sacred matters where his predecessors had kept a distance.” – Granger * Wasn’t a pragmatic religious ruler; killed priests‚ took their land‚ melted down the statue of Bel Marduk resulted in the discontinuation of the New Year’s
Premium Achaemenid Empire Babylon Battle of Thermopylae
Project Management‚ 2e (Pinto) Chapter 12 Resource Management 12.1 True/False 1) There is‚ for almost all projects‚ usually a dominant constraint that serves as the final arbiter of project decisions. Answer: TRUE Diff: 1 Section: 12.1 The Basics of Resource Constraints Skill: Definition AACSB Tag: Reflective 2) In a resource constrained project‚ the work must be finished by a certain time‚ or date‚ as efficiently as possible. Answer: FALSE Diff: 1 Section: 12.1 The Basics of Resource