Week 4 Review Questions
Review Questions

Name ________John Bailey__________

Answer the following questions (you may use MS Project Help): 1) What are the three base calendars included in MS Project and what are the default values of each?

Standard - Default base calendar, Monday to Friday, 8 to 5, lunch noon to 1. This is the default base calendar used for the project, for tasks and for resources.

Night Shift - Usually for graveyard shift, 11 PM to 8 AM, five days a week, lunch 3 AM to 4AM.

24 Hours – Work never stops here. Typically used for projects in a manufacturing situation, midnight until midnight 7 days a week.

2) What is the difference between a base calendar and a resource calendar?

Resource Calendars apply to only specific resources.

3) Why schedule one project meeting after completion of the last task, Test System?

We should - as a final meeting to discuss how the project went as a whole.

4) Give an example of when you would assign a 24-hour calendar to a resource.

24-Hour calendars would be used in situations where a consultant is being used to complete a fixed-cost task

5) If you were doing a senior project, what would be the base calendar you would use for students working on the project and what adjustments would you make to it?

The base calendar I would use would probably be the 24-hour calendar because there would not be a set time each task will be worked on.

Turn in this sheet with your MS Project file to the Weekly iLab

You May Also Find These Documents Helpful

  • Satisfactory Essays

    week 4 mgmt 404 questions

    • 295 Words
    • 2 Pages

    The three base calendars are Standard, Night Shift, and 24 Hours. Standard default values is all week days from 8 AM to 12 PM then 1 PM to 5 PM. Night Shift is All week days from 12 AM to 3 AM, 4 AM to 8 AM, and 11 PM to 12 AM. Plus Saturday from 12 AM to 3 AM, and 4 AM to 8 PM. 24 Hours is every day from 12 AM to 12 AM…

    • 295 Words
    • 2 Pages
    Satisfactory Essays
  • Better Essays

    Prg/420 Week 5

    • 958 Words
    • 4 Pages

    This tutorial is designed to provide you with an understanding of the Java Calendar class, it’s backgrounds, purpose and uses. It is created in such a manner as to allow even beginning Java programmers an understanding and feel for the uses of the Java Calendar class. The Java Calendar class was added to the Java Development Kit in JDK 1.1. It is designed to permit the conversion between a specific instance in time and a set of Calendar fields. (Oracle, 2004, 2010) What exactly does this mean? The Calendar class uses a huge array of tables to keep track of time based on daylight savings time, timezones, and calendar history, the calendar class uses a system time to determine where whatever event is being tracked falls on in the internal calendar tables. Some confusion is caused by this as Java does keep track of specific location time, and the programmer needs to keep this in mind when using the Calendar class even when it isn’t relevant to the problem being addressed (Roedy Green, Canadian Mind Products, 1196-2011).…

    • 958 Words
    • 4 Pages
    Better Essays
  • Satisfactory Essays

    7.3 Workfile

    • 255 Words
    • 2 Pages

    Discuss whether or not writing a list and keeping a calendar would make you more efficient and productive. Why or why not?…

    • 255 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    MIS 101 study guide

    • 2160 Words
    • 9 Pages

    A scheduling calendar outside a conference room is an example of an ___ that does not require a computer…

    • 2160 Words
    • 9 Pages
    Powerful Essays
  • Good Essays

    Sampling and Work Study

    • 1135 Words
    • 5 Pages

    A. How many hours are you scheduled to work each week? Answer to the nearest hour.…

    • 1135 Words
    • 5 Pages
    Good Essays
  • Good Essays

    Assignment 1 Answers

    • 1037 Words
    • 5 Pages

    b. discuss briefly seven different calendar effects identified in literature (your answer shall not exceed one page)…

    • 1037 Words
    • 5 Pages
    Good Essays
  • Satisfactory Essays

    Sociology culture

    • 544 Words
    • 3 Pages

    1. How does the culture of the Trobiand Islander affect their way of creating a calendar?…

    • 544 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    mgt 250

    • 550 Words
    • 3 Pages

    63-64) Assignment 3 Following are cost and schedule data for a project that is underway. Month 1 Planned 30 Actual 10 Task A B C D E F 2 35 25 3 42 47 Planned start Beginning Month 1…

    • 550 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Nursery Job Description

    • 437 Words
    • 2 Pages

    This is a full-time and the standard workday and work hours are Monday through Friday, 7:00 a.m. through 3:30 p.m. and some weekend work may be required and requested.…

    • 437 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    5 3 work file

    • 427 Words
    • 2 Pages

    Discuss whether or not writing a list and keeping a calendar would make you more efficient and productive. Why or why not?…

    • 427 Words
    • 2 Pages
    Good Essays
  • Satisfactory Essays

    person's shift is over then the next person will come in and take over. It's…

    • 644 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Once a preliminary schedule has been developed, it will be reviewed by the project team and any resources tentatively assigned to project tasks. The project team and resources must agree to the proposed work package assignments, durations and schedule. Once this is achieved the project sponsor will review and approve the schedule and it will then be baselined.…

    • 454 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    Shift Working

    • 2483 Words
    • 10 Pages

    The International Labour Office (International Labour Organization (ILO), 1990a) defines working in shifts as “a method of organization of working time in which workers succeed one another at the workplace so that the establishment can operate longer than the hours of work of individual workers.” The European Council Directive 93/104 (1993) declares that concerning certain aspects of the organisation of working time, shiftwork shall mean any method of organising work in shifts whereby workers succeed each other at the same work stations according to a certain pattern. Shiftworker shall mean any worker whose work schedule is part of shiftwork.” Besides these definitions, in the scientific literature, the term “shiftwork” has been widely used and generally includes any arrangement of daily working hours other than the standard daylight hours (7/8 am – 5/6 pm). In most cases, shiftwork is synonymous of irregular, odd, flexible, variable, unusual, non-standard working hours.…

    • 2483 Words
    • 10 Pages
    Powerful Essays
  • Satisfactory Essays

    Tt2Daca

    • 296 Words
    • 2 Pages

    Day Venue 8am 9am 10am 11am 12 pm 1pm 2pm 3pm 4 pm 5pm 6pm 7pm 8pm…

    • 296 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    shuttle bus 2 2

    • 250 Words
    • 3 Pages

    Aware of the difficulties that travellers have with transportation and budget, Youth Escapade has cooperated with Rapid Penang and provided mini shuttle busses to help its’ customers arrive to the town corresponding to the location of their booked accommodation safely at ease.…

    • 250 Words
    • 3 Pages
    Satisfactory Essays

Related Topics