Preview

Traditional Project Delivery Method

Good Essays
Open Document
Open Document
763 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Traditional Project Delivery Method
Project Delivery Method
The selection of a project delivery method is likely to be influenced by an array of things including –
Standard/common practices used by the principal i.e. if the delivery method worked well in the past then why change it.
The uniqueness of contracting roles and responsibilities.
The level of documentation available before contracts are entered.
The difficulty of meeting at a contract price.
The lender’s preference (to protect their investment).
After thorough comparisons of various project delivery methods such as the traditional method, design and construct method and in house development method I came to the conclusion the best option would be the traditional method of project delivery.
Traditional project delivery is the most frequently used method for construction projects. Using this method, the owner, designer and contractor are the 3 main parties of the structure. If a project manager/construction manager is involved in the process, the designer may assist the owner in administering the construction contract, including determining project progress for payment reasons.

Reasons for the use of a Traditional project delivery method:
This method has been the standard delivery method for many years in comparison to other methods therefore it is widely applicable, well understood and has well establishes and clearly defined roles for parties involved.
Because the completion of plans and specifications is done before the award, the main contract allows the owner and contractor to make relatively accurate estimates in relation to the cost and time of the project. Other methods such as the design and construction method of project delivery make it difficult to estimate cost of a project due to the lack of documentation.
Because this is a warehouse there will most likely not be any difficult design issues in relation to its construction BUT if there were, the risk would be low because sufficient time has been provided before



References: J.Burke, Australian Standards, 2012. http://www.contracts.com.au/~contracts/standard.htm n.d, An owner’s guide to project delivery methods, 2012, CMAA. http://cmaanet.org/files/Owners%20Guide%20to%20Project%20Delivery%20Methods%20Final.pdf Rawlinsons 2013, Rawlinson 's Australian construction handbook, vol. 31. Uher, TE & Davenport, P 2009, Fundamentals of building contract management, 2nd edn, UNSW Press, Sydney. http://site.ebrary.com.ezproxy.uws.edu.au/lib/sydney/docDetail.action?docID=10370184

You May Also Find These Documents Helpful

  • Satisfactory Essays

    PMBOKV4 ITTO 42 Processes

    • 1835 Words
    • 46 Pages

    ©2009 PMServicesNW. All rights Reserved. Page 1 of 9 Project Management Process…

    • 1835 Words
    • 46 Pages
    Satisfactory Essays
  • Better Essays

    Contract Breach

    • 1284 Words
    • 6 Pages

    Uher, T., Davenport, D. (2009, Ch.8, pg.165) Fundamentals of Building Contract Management (2nd Edition), UNSW Press, Sydney, NSW, AUS.…

    • 1284 Words
    • 6 Pages
    Better Essays
  • Better Essays

    Project Management Institute. (2000). _A Guide to the Project Management Body of Knowledge (4th ed.)._…

    • 1150 Words
    • 6 Pages
    Better Essays
  • Better Essays

    Project Management

    • 844 Words
    • 4 Pages

    For the general management of this project I will be using construction managers, contract managers and lawyers, and there will be another manger in charge of the hiring of staff and all of those people will be reporting to me, the general project manager. Since this is such a long and expensive project there will need to be tight controls on time and resources to ensure that there is little to no waste. The project will be segmented into phases that will be completed or almost complete when the next phase of the project begins. This will enable better control of the project as opposed to doing things out of a logical order. You would not furnish the building before you install the carpet. The amount of phases and the degree of control of each phase will depend on the size complexity and impact of the project. The phases for now, will be simplified and will go something like this; the initiating phase where all of the proposals and budgets for each phase will be defined will be set. The next phase will include the planning process. Where all of the basic needs of the project will be defined and the management team is built and phase assignments are delegated. Then the work starts with the execution of the project and the individual projects begin in earnest. This phase has some overlapping…

    • 844 Words
    • 4 Pages
    Better Essays
  • Good Essays

    Cost - Cost will typically be determined by the consultant or contractors hourly rate multiplied by an estimated time to complete the project on time or if it is late.…

    • 1112 Words
    • 5 Pages
    Good Essays
  • Good Essays

    1.3 Explain the project-planning methodologies appropriate to the types of projects run and the tools that can be used to assist project planning and control…

    • 1213 Words
    • 5 Pages
    Good Essays
  • Powerful Essays

    Project Management

    • 1126 Words
    • 4 Pages

    Project management is one of the most important and critical tool or technique, which defines the entire course of development of any kind of project.…

    • 1126 Words
    • 4 Pages
    Powerful Essays
  • Powerful Essays

    Orion Shield Project

    • 5525 Words
    • 23 Pages

    Executive Summary The basic concepts of project management calls for proper planning, organization and the management of a variety of resources in order to successfully achieve a certain goal. One of the most important objectives of project management is the ability to deliver a product or service within a certain time constraint or “on time” as well as being fiduciary responsible or “within budget.” Thus, it can be seen that good project management makes efficient use of time, money, personnel, materials and supplies, and methods of communication in order to successfully complete a project. Unfortunately, these basic methods of project management were not…

    • 5525 Words
    • 23 Pages
    Powerful Essays
  • Better Essays

    The extent and nature of contract administration varies from contract to contract. There are factors that influence the degree of contract administration, the type of contract, which includes the nature of the work, and the experience, and commitment of the personnel involved. Contract administration begins with developing clear, concise performance-based statements of work and…

    • 1049 Words
    • 5 Pages
    Better Essays
  • Powerful Essays

    As the name describes, there are three primary phases: design, bid, and build. It also has three primary contractual parties: the owner, the architect, and the contractor. Through this method of delivery, two separate contracts exist, owner to designer/architect and owner to contractor. There is not a formal contract between the contractor and the architect but there is a need for collaboration between the two. The owner and the architect execute a contract for design, the production of construction documents, and administration of the construction process at the beginning of the project. The owner is responsible for communicating to the contractor the plans and specs. The contractor is then responsible for building the project as was designed. It is also important to note that the owner is responsible for any differences between the plans and specs and must understand what is required for performance. This method is considered universal, easy to understand, and has clearly defined roles for the parties involved. One downfall to the design-bid-build process is it may have a longer duration compared to other delivery methods, for all the design work must be completed before soliciting the construction bids. In the design-bid-build delivery system it is common for the general contractor to not perform all the work with their own…

    • 1873 Words
    • 8 Pages
    Powerful Essays
  • Powerful Essays

    Chunnel Project

    • 9442 Words
    • 38 Pages

    This case study was originally prepared as part of Project Management Applications, the capstone course of the Master of Science in Project Management in the Department of Management Science at The George Washington University, by the graduating students listed above with the supervision of Professor Anbari.…

    • 9442 Words
    • 38 Pages
    Powerful Essays
  • Better Essays

    Gray, Clifford F.; Larson, Erik W., Project Management – The Managerial Process, Copyright © 2001 by The McGraw-Hill Companies, Inc.…

    • 1249 Words
    • 5 Pages
    Better Essays
  • Powerful Essays

    Bibliography: Sidney M. Levy (2002) Project Management in Construction Project Planning, Management and Delivery | Whole Building Design McGraw-Hill, 2002.…

    • 2275 Words
    • 10 Pages
    Powerful Essays
  • Powerful Essays

    Design-­‐Build Project Delivery Method DEFINITION The term “Design-­‐Build”, is used to refer to the procurement process in which an owner of a project establishes a contractual relationship with a single entity for both design and construction services. The entity, or “designer-­‐builder”, is not only responsible for the construction phase but also the design of the project. The Design-­‐Build entity can be arranged in many ways depending on the agreements established between the owner and the Design-­‐Builder. For example, the design-­‐builder may be a single company or it may be a consortium or joint venture.…

    • 3220 Words
    • 13 Pages
    Powerful Essays
  • Better Essays

    Construction Management

    • 1103 Words
    • 5 Pages

    Construction contracts structure the way in which construction is purchased. There are variety between construction purchasing system and buying something in a store for instance mobile phone or sofa. When we have the finished product available for our inspection, we can decide whether it meets our requirements. Since the final product is available, we can purchase it from a single store. With the construction it works different. The facility is purchased before it is „manufactured” based on set of drawings and work descriptors. Finally item requires the purchaser to coordinate many entities to include:…

    • 1103 Words
    • 5 Pages
    Better Essays