Risk assessment of Euro Tunnel
executive summary

The Channel Tunnel linking England with France is a superb technical and engineering achievement. However, as a business project it has undoubtedly been a failure. Shareholders in the company operating the concession for the tunnel have witnessed significant loss of value in their equity stake in the company. In 1967 proposals were invited for private financing and construction of the tunnel, with 70 - 90 % of the loans guaranteed by the British and French governments; once operational the facility was to be government owned.

In June 1982 the governments accepted an offer by an Anglo-French financing group to study the feasibility of privately financing the fixed link. This reported in May 1984, concluding that the bored tunnel option was best. Since there was no natural owner for the project, the banks felt that the chance of getting a significant portion of equity into the scheme was slim. Some level of EEC or government support would be necessary, they believed, given the size and novelty of the project, but some form of risk sharing between the private and public sectors might also be possible. On 30 November 1984, Mrs. Thatcher and President Mitterrand announced their enthusiasm for a fixed link between their two countries, provided it was financed, built and operated by the private sector. The timetable set by the two governments was tight. French parliamentary elections were scheduled for March 1986 and the French presidential election for 1988, which was also the latest year for a general election in the UK.

Under-staffing was an immediate and serious problem with eventual approval. Since the project was contractor-originated, the question immediately arose (as it always does on BOO(T) projects) of how to set up a strong owner organization independent of the sponsoring contractors that could give direction, manage the contractors and



References: Genus, A. 1997. Managing large-scale technology and inter-organizational relations: the case of the Channel Tunnel. Research Policy 26, 169-189. Taken from the Management of Projects by Peter W G Morris published by Thomas Telford, London, in 1994 The Euro-star and The Channel Tunnel; Patrick Hereford http://ocw.mit.edu/NR/rdonlyres/Civil-and-Environmental-Engineering/ 1-011Spring-2005/debassay_paper.pdf UMIST, MEng.450 Case Study”, The Channel Fixed Link:, Graham M. Winch. http://www.google.co.uk/search?hl=en&sa=X&oi=spell&resnum=0&ct=result&cd=1&q=stakeholders+of+project+channel+tunnel&spell=1 http://www.arup.com/tunnels/skill.cfm?pageid=2715 Grant, M., 1997. Financing Eurotunnel. Japan Railways & Transport Review April, 46-52. Lemley, J., 1995. Managing the Channel Tunnel – Lessons learned. Tunnelling and Underground Space Technology 10 (1), 9-11. Kirkland, C., 1995. The Channel Tunnel – Lessons Learned. Tunnelling and Underground Space Technology 10 (1), 5-6. Winch, G., 1998. The Channel fixed link: le projet du siècle. Unpublished case study. Manchester University.

You May Also Find These Documents Helpful

  • Good Essays

    The Tunnel Movie Analysis

    • 709 Words
    • 3 Pages

    So they had to create a system where when the security guard was furthest away, he would tug on a thirty-foot piece of rope to signal to the man it was clear to come out of the tunnel. At one point, there was an air raid and the lights in the tunnel went out, the ‘Tunnel Kings’, Danny and Willie, the men who were in charge of creating the tunnel were traveling through. Danny was surprisingly claustrophobic and held up the tunnel momentarily during the best time to sneak out-during the dark. It was going smoothly until one man fell on his package he was taking with him. The guards heard him and the tunnel was shut down.…

    • 709 Words
    • 3 Pages
    Good Essays
  • Good Essays

    7.05h World History

    • 447 Words
    • 2 Pages

    The Chunnel is an undersea railway linking England to France. It is 34.1 miles long crossing the English Channel. The Channel Tunnel possesses the longest undersea portion of any tunnel in the world. The tunnel carries high-speed Eurostar passenger trains. The successful project, organized by Eurotunnel, began construction in 1988 and opened in 1994.…

    • 447 Words
    • 2 Pages
    Good Essays
  • Good Essays

    the tunnel of samos

    • 521 Words
    • 3 Pages

    proposed tunnel and ending at the other, main-taining a constant elevation, as suggested by the…

    • 521 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    The Corsham tunnels are a network of concealed passageways located deep underground in the small town of Corsham. Over the years the tunnels have been used for several different purposes. At first the tunnels were a series of quarries but later they were connected and adapted to serve storage uses required by the military. Later in the twentieth century the tunnels were adapted again to act as a safe house for the government in the event of a nuclear war.…

    • 1936 Words
    • 6 Pages
    Powerful Essays
  • Good Essays

    Natural Bridge Cavern

    • 459 Words
    • 2 Pages

    Additional drilling and exploration of the property continued to take place after the cavern opened. During 1968 drilling to the south of the main cavern detected a void that was then explored. The exploration of first one cavern and then later a second cavern led to the development of the Southern caves.…

    • 459 Words
    • 2 Pages
    Good Essays
  • Better Essays

    Big Dig Research

    • 1034 Words
    • 4 Pages

    The Big Dig was a megaproject in Boston that consisted in rerouting the Central Artery into a 3.5-mile tunnel, building the Ted Williams Tunnel, the Leonard P- Zakim Bunker Hill Memorial Bridge over the Charles River, and the Rose Kennedy Greenway in the newly vacated space. The project took 15 years to get done and finally concluded on December 2007. Even though there were several issues and problems along the way that today teach us lessons about managing megaprojects including increase of cost estimations, risk control and collaboration between the involved groups, the Big Dig was a success considering its complexity and technical challenges.…

    • 1034 Words
    • 4 Pages
    Better Essays
  • Good Essays

    Twin tunnels

    • 1242 Words
    • 5 Pages

    The goal of the Twin Tunnels is to divert water from the Sacramento River, and around the Bay and delta area to distribute it to San Joaquin Valley agriculture business and also Southern California's cities and surrounding areas. The total cost of the project is estimated to be above $69 billion. State officials are want to try to put the project in without voter approval. The tunnels are a part of a restoration idea called the "Bay Delta Conservation Plan" or the "(BDCP)". While the "BDCP" tells people that the projects are a “conservation measure,” the only actual benefits are "state and federal water contractors who consider their water supplies unreliable" and also the union who would employ the workers for this project. Basically, the habitat conservation and restoration part of the "BDCP" is not much more than a "overpriced9 project that will destroy the Delta. And to add on to all of this if the Twin Tunnels do not deliver water at a reasonable cost, the undefined financing for the project would most likely make for a massive tax bill for ratepayers, taxpayers, and water agencies. This would place a large economic struggle on the State of California, and their approval would be far from positive response. In the event of the utility companies failing to par or being sued, the property owners in the areas that contain this project and the state treasury will be responsible to repay the costs.…

    • 1242 Words
    • 5 Pages
    Good Essays
  • Good Essays

    The Chunnel

    • 385 Words
    • 2 Pages

    Just getting started on the Channel Tunnel was a monumental task. Funds had to be raised (over 50 large banks gave loans), experienced engineers had to be found, 13,000 skilled and unskilled workers had to be hired and housed, and special tunnel boring machines had to be designed and built.…

    • 385 Words
    • 2 Pages
    Good Essays
  • Best Essays

    Abstract: Although China is often hailed by the rest of the world because of their quick decision-making and execution there is also the other side of China 's construction policy. There are a lot of cases where decision-making takes a long time. Because of the many actors involved and many layers of government who need to approve a project before it starts, delays can easily take years. This paper unveils the different actors involved and their interactions in Chinese construction policy. It also tries to find an answer to the research question: How do delays in Chinese construction policy occur? It will do so by analyzing the actors and their problematic ties in the Harbin subway case. Introduction: China is building complete cities within years, while other projects take years and years to even start. Where does this difference come from and which actors are involved. In order to examine the problem I 've selected the Harbin subway case. The main question in this paper will be: What caused the huge delays in the Harbin subway project? In order to examine the problem I 've split the paper into 3 parts. First I 'll give a history overview in which the events in the Harbin subway case are chronologically shown. Secondly I 'll look at all the actors involved and examine their role, interactions with other actors and complicated ties to other actors. At the end of the document I 'll finish by discussing the problem and giving my conclusion. History: The Harbin metro system has a long history of decision making. The first steps to create the Harbin subway system date back to the year 1973. In this year political tensions between Soviet Russia and China rose. In a reaction to this China decided to start "Project 7381" an air…

    • 4684 Words
    • 19 Pages
    Best Essays
  • Powerful Essays

    Shaft construction describes the building of vertical openings such as Raises and shafts. Shafts are vertical openings used for supplying equipment, personnel and support systems in the horizontal tunnel where the pipeline is installed.…

    • 1421 Words
    • 6 Pages
    Powerful Essays
  • Powerful Essays

    Tribasa Toll Road Project

    • 2844 Words
    • 12 Pages

    3. How was the transaction structure designed to minimize investor exposure to project risk? ……………………………….....7…

    • 2844 Words
    • 12 Pages
    Powerful Essays
  • Powerful Essays

    Lusoponte, a consortium (Portoguese, British and French) companies, won the international public Tender process set by GATTEL (inter-ministerial agency) which made the decision for the location of the bridge…

    • 3582 Words
    • 14 Pages
    Powerful Essays
  • Powerful Essays

    Road concession contracts provide one way of delivering roads that differ significantly from the more traditional means of designing and calling for state-funded conventional construction tenders. Concession contracts can provide some significant benefits over conventionally-funded construction projects but they also create their own unique set of problems that need to be dealt with to ensure value for money and a successful outcome for the user and sponsor. This paper provides some insight into the various problems and opportunities that are created by concession contracts. Several of these aspects are discussed in the context of the newly completed N4 Maputo corridor toll road and the contractual and quality issues that emerged during the initial construction phase of the project. The issues are put forward for debate and discussion with a view to providing input into future contracts and into the remaining operational period of some of the current concession contracts.…

    • 5078 Words
    • 21 Pages
    Powerful Essays
  • Satisfactory Essays

    STUDY GUIDE FOR HKU SE

    • 851 Words
    • 4 Pages

    CIVL6061 Special topic in environmental engineering A: Research and practice Room: LE-8 Room: KK-LG104 Room: LE-2 Room: MW-103 Room: KK-LG104 7:00-9:30 pm 7:00-9:30 pm 7:00-9:30 pm 2:30-5:00 pm 2:30-5:00pm CIVL6083 Practical design and construction of tunnels in Hong Kong CIVL6054/ GEOG7006…

    • 851 Words
    • 4 Pages
    Satisfactory Essays
  • Powerful Essays

    ultimately, allowed the entire tunnel industry to approach complex excavations in a safe and cost…

    • 4450 Words
    • 18 Pages
    Powerful Essays