Om Case Analysis Executive Shirt Company
Q.1 Compute the following quantities for the current production process as well as for Mike’s and Ike’s plans, assuming the plans are implemented as described in the case. (50 points)

| Current ProcessRegular Shirts | Mike’s PlanRegular & Custom Shirts | Ike’s PlanRegularShirts | Ike’s PlanCustom Shirts | Actual Cycle Time (min/shirt) | 0.5 | 0.5 | 0.67 | 3.9 | Manufacturing Lead Time (days) | 0.815 | 0.052 | 1.056 | 0.058 | WIP inventory (shirts) | 11760 | 1980 | 9060 | 48 | Production Capacity (shirts/day) | 960 | 960 | 720 | 123.07 | Capacity Utilization | 83.33 | 93.75 | 111.11 | 81.25 | Direct Labour Content (min/shirt) | 26.51 | 26.45 | 26.51 | 26.01 | Direct Labour Utilization | 69.04 | 76.22 | 90.17 | 33.87 | Direct Labour Cost ($/shirt) | 3.84 | 3.47 | 3.43 | 7.68 |

Assumption: Throughout the case, it has been assumed that there is no specialization, i.e. the work performed by all workers in a station is similar.
Each of the cases has been analysed separately, the quantities asked in the table have been calculated for each case, and filled in the above table.
Current Process
The details of the process, as given in Exhibit 3, have been reproduced, along with the run time and the time taken for each batch for each process have been calculated and shown in the table below

Operation | Labour Content (min/shirt) | Number of Workers | Cycle Time (min/shirt) | Time taken for 1 batch (min) | | | | | Regular | Custom | Make collar | 3.90 | 8 | 0.4875 | 29.25 | 2.4375 | Make cuffs | 2.00 | 4 | 0.5 | 30.00 | 2.5 | Make sleeves | 0.65 | 2 | 0.325 | 19.50 | 1.625 | Make front | 2.50 | 6 | 0.416 | 25.00 | 2.08 | Make back | 1.70 | 4 | 0.425 | 25.50 | 2.125 | Join shoulders | 0.66 | 2 | 0.33 | 19.80 | 1.65 | Attach collar | 1.65 | 4 | 0.4125 | 24.75 | 2.0625 | Attach sleeves | 1.55 | 4 | 0.3875 | 23.25 | 1.9375 | Stitch sleeves | 0.65 | 2 | 0.325 | 19.50 | 1.625 | Sew sideseam | 1.80 | 4 | 0.45 | 27.00 | 2.25 |

You May Also Find These Documents Helpful

  • Good Essays

    2-9 (Key Question) Assume that a business firm finds that its profit it greatest when it produces $40 worth of product A. Suppose also that each of the three techniques shown in the table on page 43 will produce the desired output.…

    • 673 Words
    • 3 Pages
    Good Essays
  • Good Essays

    3.09 Honors Chem Online

    • 536 Words
    • 3 Pages

    Here is sample data and how you would do the calculations. Of course, you will need to use your data, but you can follow along step-by-step.…

    • 536 Words
    • 3 Pages
    Good Essays
  • Good Essays

    6.03 chemistry

    • 736 Words
    • 5 Pages

    Insert a complete data table, including appropriate significant figures and units, in the space below. Also include any observations you made over the course of Part I.…

    • 736 Words
    • 5 Pages
    Good Essays
  • Good Essays

    (1) TIME ALLOWED – 3 Hours (2) TOTAL NUMBER OF QUESTIONS – 6 (3) ANSWER ALL QUESTIONS (4) THE QUESTIONS ARE OF EQUAL VALUE (5) THIS PAPER MAY NOT BE RETAINED BY THE CANDIDATE (6) ONLY CALCULATORS WITH AN AFFIXED “UNSW APPROVED” STICKER MAY BE USED (7) STATISTICAL FORMULAE ARE ATTACHED AT END OF PAPER STATISTICAL TABLES ARE ATTACHED AT END OF PAPER…

    • 10483 Words
    • 42 Pages
    Good Essays
  • Better Essays

    Hilcrest Auto Case

    • 973 Words
    • 3 Pages

    machine takes 0.06 seconds per tube (60 seconds per 1000 tubes). Each of these processes runs…

    • 973 Words
    • 3 Pages
    Better Essays
  • Good Essays

    ECO 550 FINAL EXAM

    • 1177 Words
    • 4 Pages

    7. A plant manager is attempting to determine the production schedule of various products to maximize profit. Assume that a machine hour constraint is binding. If the original amount of machine hours available is 200 minutes., and the range of feasibility is from 130 minutes to 340 minutes, providing two additional machine hours will result in the:…

    • 1177 Words
    • 4 Pages
    Good Essays
  • Better Essays

    1) Prepare the manufacturing staff’s calculations for the three alternatives (please refer to the attachments):…

    • 1278 Words
    • 6 Pages
    Better Essays
  • Satisfactory Essays

    Tanglewood Case 2

    • 413 Words
    • 2 Pages

    Based on the environmental data, some factors that suggest Tanglewood might have difficulty filling positions is based on retail work is not desirable to recent college graduates. Tanglewood would like to hire those that can start lower at shift level and move up the chain and have college background. However retail is not the more desirable market since it has long hours, low pay, and conflict with lower-level employees.…

    • 413 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Provide detailed descriptions and show all calculations used to arrive at solutions for the following questions:…

    • 613 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    through the lab fill in the table below. Use this information to answer the questions that follow…

    • 772 Words
    • 8 Pages
    Powerful Essays
  • Satisfactory Essays

    1. Draw a detailed process flow map of the current process at Receiving Plant #1. What is the capacity of each process step?…

    • 426 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    why not!

    • 471 Words
    • 2 Pages

    Insert a complete data table, including appropriate significant figures and units, in the space below. Also include any observations you made over the course of Part I.…

    • 471 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Case Study Specialty Toys

    • 647 Words
    • 3 Pages

    3. Compute the projected profit for the order quantities suggested by the management team under three scenarios: worst case in which sales = 10,000 units, most likely case in which sales = 20,000 units and best case in which sales = 30,000 units:…

    • 647 Words
    • 3 Pages
    Good Essays
  • Good Essays

    BUS 475 Sample Final Exam

    • 4935 Words
    • 20 Pages

    Jaime Inc. manufactures 2 products, sweaters and jackets. The company has estimated its overhead in the order-processing department to be $180,000. The company produces 50,000 sweaters and 80,000 jackets each year. Sweater production requires 25,000 machine hours, jacket production requires 50,000 machine hours. The company places raw materials orders 10 times per month, 2 times for raw materials for sweaters and the remainder for raw materials for jackets. How much of the order-processing overhead should be allocated to jackets?…

    • 4935 Words
    • 20 Pages
    Good Essays
  • Satisfactory Essays

    This assignment is in two parts. First fill out the table. Then use the information in the table to answer the journal question.…

    • 380 Words
    • 2 Pages
    Satisfactory Essays

Related Topics