Preview

Nt1310 Project Management Assignment

Best Essays
Open Document
Open Document
3148 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Nt1310 Project Management Assignment
Project management assignment

Table of Contents

1.0 Introduction
The essay discusses basic prices of project management. The first part tackles the initial technical aspect of project planning where scheduling is done to determined logical flow of activities. At this stage, a critical path is determined and project is visualised using Gantt chart and network diagram. Importance of network diagrams is also discussed. The second case discusses general skills and competencies that are needed to successful project management. A range of skills are classified by various authors. In this article, skills that are discussed include technical, communication, people management, and leadership and motivation skills.
…show more content…
This was calculated by calculating the time of all possible critical paths and taking the shortest. A project could have more than one critical path on basis that it carries activities from beginning to the end. The time of all critical activities was carried added to the beginning date (9 May 2011), excluding weekends.
2.6 Effect of the duration of the project if the following happened:
a) If P delayed by 1 day: This would not affect duration of the project, it is not a critical activity. The slack time is not zero in this and therefore has no effect on duration of the project duration or completion date.
b) If activity Q is delayed 1 day, the project duration would also not be delayed. Also, Q is not a critical activity considering that its ES≠LS and EF≠LF. ES-LS and EF-LF=1, hence not a critical path because of the one day float.
c) A 2 day delay during activity M would not affect the duration of the project. ES≠LS and EF≠LF. ES-LS and EF-LF=2, which means the activity has a float of 2 days which means the project can be delayed by this duration without affecting the schedule of completion
…show more content…
However, depending in the goal to be achieved, it is also one of the most challenging but which need to be managed effectively if it is to succeed. The reason why projects become imperative in any organisation is because an organisation has basic roles such as maintaining profitability and customer relationships which must be maintained while at the same time, they have to change or undertake new frontiers to enhance the stated and other objectives. Hence, there is need to balance all these parallel tasks effectively (Grande-Bretagne,

You May Also Find These Documents Helpful

  • Satisfactory Essays

    What is the slack time (float) for activity A? (1 points) d) What is the slack time (float) for activity D? (1 points) e) What is the slack time (float) for activity E?…

    • 556 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    PROJ 586 Final Exam

    • 872 Words
    • 4 Pages

    9. (TCO C) In addition to showing the technical constraints among activities, how does the network diagram logic also take into account resource constraints?…

    • 872 Words
    • 4 Pages
    Powerful Essays
  • Satisfactory Essays

    Scheduled completion time = 20 weeks Critical Path = B, C, D, F, H c. What is the slack time (float) for activities A, D, E, and G? A=3 weeks D=0 weeks E=2 weeks G=3 weeks…

    • 562 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    AIB Simulation

    • 771 Words
    • 4 Pages

    Before starting this homework assignment, please review the AIB simulation in this week’s Lecture. This simulation will provide you with an understanding of how to create a network diagram, and how to do a forward and backward pass to determine the ES, LS, EF, LF and slack (float). You will also learn how to determine the duration of the project, and the critical path.…

    • 771 Words
    • 4 Pages
    Satisfactory Essays
  • Powerful Essays

    The critical activities are B, C, E, F, H, J and K. The project should be completed (earliest finish) in 43 weeks - therefore R.C. Coleman’s 40 week completion time cannot be achieved. The probability of R.C. Coleman meeting the 40 week deadline is ~10%. This is a low chance, so they should be cautioned if they make 40 weeks their deadline.…

    • 656 Words
    • 3 Pages
    Powerful Essays
  • Good Essays

    Pm Tests

    • 443 Words
    • 2 Pages

    b) If the project schedule is relaxed or lengthened, what is the impact on quality? (15 points) (Points : 30)According to the triple constraints: "Scope, Time, Cost". All three of these impact the quality depending on which trade off is affecteda) The longer a project takes to complete, the more it will impact the quality of the project as a whole. b) Being relaxed or expanding the time frame for completion will impact scope and cost. Why? More money and less time to complete the work package deliverables.…

    • 443 Words
    • 2 Pages
    Good Essays
  • Good Essays

    Natural Blends

    • 556 Words
    • 3 Pages

    Project Management Case Assignment - Use Microsoft Project to analyze this case. This is an example of a construction project. The construction for a large corporate building must be started by February 15th and completed by the end of the year. The legal contract for the project includes a penalty of $10,000 for every week of delay beyond December 31st. The details of the project activities are as follows – The project begins with clearing the site, an activity that takes eight weeks. Once the site is cleared, laying of the subsurface drainage takes another eight weeks, followed by filling of the earth which takes 14 weeks. Only after this activity is completed can installation of the artificial turf outside of the building can start – the task then takes 12 weeks. Simultaneously, the work on the building can also start once the site is cleared. The work on the building starts first by excavating and then by pouring of the concrete basement. Each of these activities takes 4 weeks to complete. Next comes the construction of the walls (12 weeks), followed by constructing the roof (13 weeks). The interiors are then completed (5 weeks) followed by internal painting (4 weeks). However, painting cannot be started until electrical work is completed (4 weeks). The electrical work cannot be started until the outside power lines are laid (8 weeks), which needs an additional activity of getting the permits before it can be started. The permit takes 4 weeks. Assume that you would start on the permits after the excavation activity for the building begins. Once the roof of the building is erected, work can start simultaneously on the outside lighting (5 weeks), and on the signage and other external landscaping (4 weeks). For simplicity, assume you start the project on February 15th, 2010 which is a Monday and that you work five days a week for 8 hours every day. Analyze the following questions based on the estimates of the above activities 1) When do you complete the project?…

    • 556 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    Educare Ltd Project Report

    • 3316 Words
    • 14 Pages

    The Project Duration is the time taken to complete the whole project. In this project, it will be 40 days. This is done by adding the number of days from Activity A to R. When there are multiple activities, the latest time is taken.…

    • 3316 Words
    • 14 Pages
    Powerful Essays
  • Satisfactory Essays

    Space Constructors

    • 570 Words
    • 3 Pages

    1. Reduce total project duration as much as possible without unnecessary additional cost. Indicate the new critical path or paths. Show how much slack or float remain in the noncritical paths.…

    • 570 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Critical Path

    • 1605 Words
    • 7 Pages

    10. The earliest finish time for the last activity in the project identifies the project completion time.…

    • 1605 Words
    • 7 Pages
    Satisfactory Essays
  • Satisfactory Essays

    a) From the following logic table draw a fully analysed (AON) network diagram for the…

    • 416 Words
    • 5 Pages
    Satisfactory Essays
  • Satisfactory Essays

    (B.) What is the slack time (float) for activities A, D, E, and G? [8 points] (Points: 15)…

    • 692 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Critical Path

    • 1047 Words
    • 5 Pages

    As audit of liquid assets (activity 4) is not on the critical path, it is not a critical activity. This slack job has a slack time of 178 hours for which slack time= late start time – early start time (231-53) = late finish time – early finish time (266-88).…

    • 1047 Words
    • 5 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Homework

    • 424 Words
    • 2 Pages

    9. These can be calculated in a forward pass on an activity-on-node network (AON): D…

    • 424 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Project Proposal

    • 523 Words
    • 3 Pages

    Business minded people and tourist. If the botanical garden’s beauty was restored successfully. Tourist will enjoy and stay, so business minded people may put up a store inside the botanical for the convenience of the tourist.…

    • 523 Words
    • 3 Pages
    Satisfactory Essays

Related Topics