1. Draw the network diagram (use activity on the node).
2. Explain how you determined the timing of activities and the total float.

From the work of Field and Keller (1998), there are some relationships among EST, EFT, LST, LFT, duration and TF in an activity-on-node. (See Table 1) Meanwhile, there are some types of dependency, but finish-to-start lag is normal one. In the network diagram drawn, it uses the finish-to-start relationship.

Earliest Finish Time(EFT) = Earliest Start Time(EST) + Duration
Latest Start Time(LST) = Latest Finish Time(LFT) - Duration
Total Float(TF) = Latest Finish Time(LFT) - Earliest Start Time(EST) - Duration

Table 1: The relationships among EST, EFT, Duration, LST, LFT and TF (Field and Keller, 1998, pp.197-202)

In terms of the timing of activities, Maylor (2003) thinks that it includes the forward pass and reverse pass. In forward pass, it begins at the left-hand side of the diagram with the earliest start time for the initial activity, which is zero. The next activity cannot begin until the first activity has completed. So the early start of activity A is zero. Owing to 4 days duration, the earliest finish time of activity A is 4 days. Adding the duration of each activity, EFT of final activity Q is 88 days. In reverse pass, it begins from the end of the network i.e. 88 days and allocates the LSTs for each activity. According to Turner (1999), in the back pass, the early finish of last activity transfers to its late finish. Total float equals to late start date minus early start date.

3. Explain how you determined the project duration and the critical path.
According to Gray & Larson (2006), they think that the earliest finish time of the final activity of project in the forward pass is identified as the project duration through beginning at the first activity and then adding the activity duration. In the network diagram drawn, the project duration is 88 days.

In the work of Turner (1999), the critical path

You May Also Find These Documents Helpful

  • Satisfactory Essays

    The following data were obtained from a project to design a new software package: Activity Duration Predecessors A 5 Days --- B 8 Days --- C 6 Days A D 4 Days C, B E 5 Days A F 4 Days D, E, G G 4 Days B, C H 3 Day G Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) Calculate the…

    • 556 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    PROJ 586 Final Exam

    • 872 Words
    • 4 Pages

    12. (TCO C) Calculate the earliest start for Task B if its predecessor, Task A, finishes on day 3 and the duration of Task B is 2 days.…

    • 872 Words
    • 4 Pages
    Powerful Essays
  • Best Essays

    Is3350 Unit 1 Assignment

    • 3307 Words
    • 14 Pages

    In order to calculate the timing of an activity ‘Duration’ of the activity needs to be summed up with the ‘Earliest Finish…

    • 3307 Words
    • 14 Pages
    Best Essays
  • Satisfactory Essays

    CMGT 410 Week 4 Resources

    • 508 Words
    • 3 Pages

    Gantt diagram showing duration estimates for all tasks and their sequencing (including precedence relations) and highlighting any critical path(s) arising from task dependencies ultimately determining the minimal duration of a project…

    • 508 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    AIB Problem

    • 565 Words
    • 3 Pages

    e ) What is the slack time (float) for activity E? (1 points) Answer: 4 days f)…

    • 565 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    operation management

    • 252 Words
    • 1 Page

    To conclude, we cut activity T by 2 weeks. The project can be completed in 14 weeks.…

    • 252 Words
    • 1 Page
    Satisfactory Essays
  • Satisfactory Essays

    Finding 1: Using the estimated times collected by the project team, the preliminary information for activities with duration times and predecessors can be seen in the Activity-on-Node (AON) model that…

    • 401 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    Dragonfly case study

    • 1041 Words
    • 5 Pages

    2. The red dotted line represents the circular dependency between activity A4 and activity A9.…

    • 1041 Words
    • 5 Pages
    Powerful Essays
  • Good Essays

    Marketing

    • 857 Words
    • 4 Pages

    Which environmental forces sociocultural, economic, political, legal, regulatory social ethical, competitive, or technical, might a marketer need to consider when marketing the following products in the international marketplace and why?…

    • 857 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    hard rock

    • 276 Words
    • 2 Pages

    1. The Critical Path with no slack time is A-B-D-E-F-G-O. The project would take a total of 34 weeks ending at activity O.…

    • 276 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    As the activity B does not located on critical path, therefore the completion time no change even its shorten one week. For the activity G which is located on both critical path 2(ACFGI) and 3(ADFGI), therefore it is key activity for the project and has to shorten. Due to activity C and D is location on critical path 2(ACFGI) and 3(ADFGI) respectively, if only shorten activity C or D then another one become critical path, therefore both activity C and D have to shorten one week at same time. Conclusion, I would choose activity C, D and G to shorten the completion time as above reasons.…

    • 427 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Decision Analysis

    • 807 Words
    • 4 Pages

    Question 1: R.C. Coleman’s top management established a required 40 week completion time for the project. Can this completion be achieved? Include probability information in your discussion. What recommendations do you have if the 40 week completion time is required?…

    • 807 Words
    • 4 Pages
    Good Essays
  • Good Essays

    Dore-Dore Q&a

    • 466 Words
    • 2 Pages

    In traditional operation, the total throughput time is 6 weeks, for a 5 day week, that is 30 days…

    • 466 Words
    • 2 Pages
    Good Essays
  • Good Essays

    Sim 335

    • 642 Words
    • 3 Pages

    Earliest start time (EST) and earliest finish time (EFT), which are done calculating in a forward pass through the network, starting from the Start node way down to the Finish node. The very first task node always has its EST equal to 0, and its EFT will be calculated following the function:…

    • 642 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    managing projects

    • 3062 Words
    • 13 Pages

    From the diagram above, the ES or earliest start time is zero for activity A. Therefore, ES equals the EF or earliest finish time of the predecessor. An example can be from the diagram above as ES of C activity is EF of activity B i.e. 9 days. Earliest finish time is computed when the duration of any activity is added to the earliest start time. The equation will be:…

    • 3062 Words
    • 13 Pages
    Powerful Essays

Related Topics