Due: August 12th
Discussion Questions
1.-What is the difference between a gross requirements plan and a net requirements plan? 2.-What are the differences between MRP & MPS?
3.-MRP is more than an inventory system, what additional capabilities does MRP possess? 4.-What functions of the firm affect a MRP systems? How?
5.-How does MRP II differ from MRP?
6.-What are the differences between SOP & MPS?
7.-What is the meaning of Bill of Material ?
Problems
1. You have developed the following simple product structure of items needed for you gift bag for a rush party, for prospective pledges in your organization. Your forecast
200 attendees. Assume that there is no inventory on hand of any of the items. Explode the bill of material (Subscripts indicate the number of units required).
J
K(1)
J
M(2)
L(4)
J
444
2. You are expected to have the gift bags in Problem 1 ready at 5p.m.However you need to
)44
personalize the items(monogrammed pens, note pads, literature from the printer, etc.). The lead time is 1 hour to assembled 200 Js once the other items are prepared. The other items will take a while as well. Given the volunteers you have, the other time estimates are item K (2 hours),item L (1hour),and item M(4 hours).Develop a time-phased assembly plan to prepare the gift bags.
3. The demand for subassembly S is 100 units in week 7.Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 1 unit of V,2 units of W and 1 unit of X. Finally , each unit of U
requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make
S,1 week to make T,2 weeks to make U,2 weeks to make V,3 weeks to make W,1 week to make
X,2 weeks to make Y, and 1 week to make Z.
a) Construct a product structure, Identify all levels, parents, and components.
b) Prepare a time-phased product structure.
4. Using discrete available to promise (ATP) logic, calculate the MPS for the following conditions.
How many units are available to promise in period 4 ?
Period
One hand
Forecast
Project
20
available balance ATP(discrete)
MPS
Lot size=30, Safety stock=15 1
25
2
23
3
30
4
20
5.-Level demand
1
15
Forecast
Avaible(End)
MPS
20
On
30
Hand(start)
2
15
3
15
4
15
5
10
6
10
7
10
8
10
9
5
10
5
11
5
12
5
20
20
20
20
20
20
20
20
20
20
20
6.-
1
Forecast
10
Avaible(ending)
MPS
0
On
30
hand(starting)
2
10
3
10
4
10
5
10
6
20
7
20
8
20
9
20
0
0
40
0
0
0
40
0
7.-Rolling through time
Period
On hand
Forecast
Project
15
available balance MPS
Lot size=35
Safety stock =10 units 1
25
2
25
35
3
25
4
15
You May Also Find These Documents Helpful
-
¼ hours (20,000 x 60)/80,000 = 15 minutes 3. How many units were produced in the second quarter? 120,000 units Problem 7-54: Plantwide versus Departmental Rates, Product-Costing Accuracy: Activity-Based Costing, page 330-331 See Attached File…
- 98 Words
- 1 Page
Satisfactory Essays -
It takes 5 + 100*0.2 + 10 + 100*0.1 = 45 minutes to make 100 products.…
- 854 Words
- 4 Pages
Good Essays -
v. Update the units on hand to 50, warehouse number to 2, and unit price to $329.00…
- 2322 Words
- 10 Pages
Satisfactory Essays -
Managerial Statement: The expected duration of the project is 31 working days. Critical Activities are I, J, K, L, and M.…
- 678 Words
- 3 Pages
Satisfactory Essays -
Part B, the first step is to find the quantity demanded and quantity supplied need to be established in regards to prices provided.…
- 421 Words
- 2 Pages
Satisfactory Essays -
5. Assume that all your orders come in sizes of 1 doz. Now, you decide to fire your roommate and…
- 669 Words
- 3 Pages
Satisfactory Essays -
1. The Hola Company held a Christmas party. The company expected attendance of 100 persons and prepared the following budget:…
- 1207 Words
- 5 Pages
Powerful Essays -
23. What is the determinant of quantity demanded? What is the determinant of quantity supplied?…
- 953 Words
- 4 Pages
Good Essays -
1. The project is estimated to be completed in 260 working days. The project starts on January 2nd, 2015 and ends on January 8th, 2016.…
- 402 Words
- 2 Pages
Good Essays -
What are the key inputs to successfully implement MRP? As a result of these inputs, which…
- 334 Words
- 2 Pages
Satisfactory Essays -
units. The workstation produces this part at the rate of 200 units per day. What…
- 1231 Words
- 5 Pages
Good Essays -
After getting input from these sources, MRP logic processes the available information and gives information about the following:…
- 2537 Words
- 11 Pages
Good Essays -
The system then confirmed which materials were required to deliver these orders as well as ensure that the materials were ordered in time. During the 1980’s and 1990’s, the model of MRP was expanded and improved to warrant the amalgamation of all functions of the business, it was at this stage that the MRP I system was retitled to MRP II (Kruger & Ramphal, 2009).…
- 1268 Words
- 4 Pages
Better Essays -
Neither this documentation nor any part of it may be copied or reproduced in any form or by any means or…
- 38908 Words
- 156 Pages
Satisfactory Essays -
An often asked question: How can you convert the diameter of a round wire d to the…
- 2169 Words
- 9 Pages
Good Essays