1. Construct the CPM network described by the following set of activities, compute the length of each path in the network, and indicate the critical path.

|Activity |Time (weeks) |
|1 [pic] 2 |5 |
|1 [pic] 3 |4 |
|2 [pic] 4 |3 |
|3 [pic] 4 |6 |

2. Construct the CPM network described by the following set of activities, compute the length of each path in the network, and indicate the critical path.

|Activity |Time (weeks) |
|1 [pic] 2 |3 |
|1 [pic] 3 |7 |
|2 [pic] 4 |2 |
|3 [pic] 4 |5 |
|3 [pic] 5 |6 |
|4 [pic] 6 |1 |
|5 [pic] 6 |4 |

3. Construct the CPM network described by the following set of activities, compute the length of each path in the network, and indicate the critical path.

|Activity |Time (months) |
|1 [pic] 2 |4 |
|1 [pic] 3 |7 |
|2 [pic] 4 |8 |
|2 [pic] 5 |3 |
|3 [pic] 5 |9 |
|4 [pic] 5 |5 |
|4 [pic] 6 |2 |
|5 [pic] 6 |6 |
|3 [pic] 6 |5 |

4. Given the following network with activity times in months, determine the earliest and latest activity start times and slack for each

You May Also Find These Documents Helpful

  • Satisfactory Essays

    3. Now choose one of these strategies and perform the necessary calculation. Explain in complete sentences why you have chosen this strategy.…

    • 261 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    The following data were obtained from a project to build a pressure vessel: Activity Duration Predecessors A 6 weeks --- B 6 weeks --- C 5 weeks B D 4 weeks A, C E 5 weeks B F 7 weeks D, E, G G 4 weeks B H 8 weeks F I 5 weeks G J 3 week I Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) Calculate the scheduled completion time. (5 points) b) Identify the critical path (6 points) c)…

    • 556 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Documents NETW240 Wk4 Lab

    • 1983 Words
    • 10 Pages

    In this module you will be working on the following equipment to carry out the steps defined in each exercise.…

    • 1983 Words
    • 10 Pages
    Satisfactory Essays
  • Good Essays

    1) (2 point) In this exercise, you create the routing for your finished product, Rocker. Note the shown below. In step #5, the value of 1 is entered into the From Lot Size field.…

    • 711 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    Organic Chem

    • 521 Words
    • 3 Pages

    c. Mark points on the energy diagram corresponding to each carbocation in your mechanisms. See the blue # above.…

    • 521 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Huffman Trucking Benefits

    • 278 Words
    • 2 Pages

    The Critical Path Method will indicate the longest path of planned to the end of the project. It is a very good tool to use because it will give the Project Manager a good idea of what tasks that must be completed on time in order for the project to continue smoothly. This method is commonly used in the development of new…

    • 278 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    5. [3] Ten processes share a critical section implemented by using a semaphore x. Nine…

    • 299 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    404 Lesson 2

    • 336 Words
    • 4 Pages

    Directions: Each question of this assignment should be prepared as a separate sheet in one Excel file. Please change the sheet names at the bottom of the page to the question number. Then, follow the directions for each question below. Be sure to show your calculations and label your work for full credit. This assignment is worth 50 points. The grading rubric may be previewed in the Cost Behavior Drop Box.…

    • 336 Words
    • 4 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Comp 122 Week 1 Ilab

    • 662 Words
    • 3 Pages

    3. Design an algorithm in pseudocode to solve the problem. Make sure to include steps to get each input and to report each output.…

    • 662 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    cmis 102 HW 2

    • 748 Words
    • 6 Pages

    Using the Hierarchical Design, I am creating a flow chart or blueprint of how basically this program will work:…

    • 748 Words
    • 6 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Please complete the following five exercises below in either Excel or a word document (but must be single document). You must show your work where appropriate (leaving the calculations within Excel cells is acceptable). Save the document, and submit it in the appropriate week using the Assignment Submission button.…

    • 952 Words
    • 8 Pages
    Satisfactory Essays
  • Satisfactory Essays

    d) Each set of connections must be one full typed page. So the total length of the assignment will be 2 full pages.…

    • 383 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Subnet

    • 331 Words
    • 2 Pages

    In part 1 of the assignment, you will complete a fixed subnet design and in part 2, a variable subnet design.…

    • 331 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    C) Again, an Euler circuit would be possible. A small number of vertices to visit would make finding a path without retracing possible.…

    • 473 Words
    • 2 Pages
    Satisfactory Essays
  • Better Essays

    Your company has met with University officials to develop a list of activities required to make Rock’n Bands a reality. The list on Page 2 includes twelve activities as well as their durations and immediate predecessors. The project plan is also described visually on page 2 with a network diagram. The subscripts on each activity denote the number of weeks of work that activity is expected to require. Arrows denote the order of activities. For instance, activity E cannot be started until activity A is completed, and activity H cannot be started until both C and D are complete. The start and end nodes are dummy nodes and do not need to be worked on. Note that at the beginning of the project, activities A, C and D are available to start working on, as they have no predecessor activities. Be sure to understand the diagram before reading further.…

    • 1009 Words
    • 5 Pages
    Better Essays