Preview

Engineering Management 1

Good Essays
Open Document
Open Document
1104 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Engineering Management 1
ENGINEERING MANAGEMENT 1

ASSIGNMENT 2 - PROJECT SCHEDULING

The Sharon Construction Corporation

The Sharon Construction Company has been awarded a contract for the construction of a 20,000-seat stadium. Construction works must start by February 15 and be completed within one year. A penalty clause of $15, 000 per week of delay beyond February 15 of next year is written into the contract.
Jim Brown, the president of the company, called a planning meeting, where he expressed great satisfaction at obtaining the contract and revealed that the company could net as much as $300, 000 on the project. He was confident that the project could be finished on time with an allowance made for the usual delays anticipated in such a large project.
Bonnie Green, the director of personnel, agreed that in a normal year only slight delays might develop due to a shortage of labor. However, she reminded the president that for such a large project, the company would have to use unionized employees and that the construction industry labor agreements were to expire on November 30. Past experience indicated a fifty-fifty chance of a strike.
Jim Brown agreed that a strike might cause a problem. Unfortunately, there was no way to change the contract. He inquired about the prospective length of a strike. Bonnie figured that it would last either 8 weeks (70% Chance) or possibly 12 weeks (30% chance). Jim was not too pleased with these prospects. However, before he had a chance to discuss contingency plans Jack White, the vice-president for engineering, interrupted him. Jack commented that an extremely cold December had been predicted. This factor had not been taken into consideration during earlier estimates since previous forecasts called for milder weather. Concrete pouring in a cold December would require in one out of three cases (depending on the temperature) special heating that cost $500 per week.
This additional information did not please Jim at all. The chances for delay

You May Also Find These Documents Helpful

  • Satisfactory Essays

    Individual Assignment02

    • 988 Words
    • 5 Pages

    The arbitrator dictated the terms of the first agreement and neither the company nor the union was happy with the settlement. The term of the dictated agreement was two years and it was now time for the parties to meet and discuss the renewal of the collective agreement.…

    • 988 Words
    • 5 Pages
    Satisfactory Essays
  • Good Essays

    Is3110 Unit 4

    • 406 Words
    • 2 Pages

    If the project is completed on time then there is no risk for completion. All of the regular risks that apply to a project built on time apply to this one regardless of whether you are building a new infrastructure or modifying an older one. If the project is finished one month early, the quantitative risk really does not exist. It is basically comparable to completing the project on time. Since the project is quoted at 3 million dollars it will stay the same regardless of how fast the project is finished. However, you may see differences. When you rush a project this large you could possibly cut corners or receive poor quality results. If the project is finished two months late there are additional risks. If the company expects to make $20 million dollars annually, and assuming that the 4% penalty is levied against this yearly figure and not within smaller period of time, one month late means that US Industries Incorporated loses $800,000 annually. There doesn't appear to be any additional risk, however, further penalties and the possible eventual loss of the contract to a competitor could result in a poor product. There again appears to be no real quantitative risk involved if the project is finished a month early with the security requirements. If the originally quoted $3 million dollars remains the same regardless of how fast the project is finished and not coupled with hourly or daily wages, then there is nothing to lose financially. However the companies go beyond the required 1.5% completion benchmarks that the contract demands. Rushing a project of this scale also comes with rushed results possibly cut corners or poor quality. The credibility of the company is at stake with such a high profile, high income project such as this, and it is important to use all of the time available to ensure the best product is on display for any customer. The finished project should meet both the time and security requirements but not the service agreement. There does not…

    • 406 Words
    • 2 Pages
    Good Essays
  • Good Essays

    construction project. According to the contract, Jason has to work long hours but will get…

    • 1968 Words
    • 14 Pages
    Good Essays
  • Good Essays

    Nt1310 Unit 1 Activity 1

    • 491 Words
    • 2 Pages

    A major part of the study of labor law and collective bargaining is the unique vocabulary that has…

    • 491 Words
    • 2 Pages
    Good Essays
  • Good Essays

    Jim Brown

    • 770 Words
    • 4 Pages

    From what we can determine so far the main issues revolving around your construction project are unionized workers starting strikes and weather concerns during December. We are also informed that the company will suffer from a $500 per week penalty fee on overhead expenses if the construction project is not finished on time. It is also stated in the contract that a penalty clause of $15,000 per week of delay beyond February 15 of the following year will be implemented.…

    • 770 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    Law 531 Memorandum

    • 981 Words
    • 4 Pages

    This memo is in response to the dispute over the contract between Span Systems and Citizen-Schwarz AG (C-S). Management is taking the necessary steps in resolving the issues C-S is reporting of low quality deliverables and schedule delays. C-S is threatening rescission of their contract and demand immediate transfer of all unfinished codes (University of Phoenix, 2002, Legal Environment of Business: Contract Creation and Management, Law 531). C-S must prove a material breach is occurring and give adequate notice to Span Systems to issue a rescission (Cheeseman, 2010). Span Systems and C-S signed a one-year contract worth $6 million dollars that has five clauses for breach of contract and a project structure clause. This memo will identify what management is doing to avoid legal risks, minimize liabilities, and benefit from opportunities presented to make this contract successful.…

    • 981 Words
    • 4 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Railroad Strike Dbq

    • 383 Words
    • 2 Pages

    This strike had a big impact because the striking workers wouldn’t allow trains, mainly freight trains to roll. They had one term to make this dilemma get dropped; drop the third wage cut.…

    • 383 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Facts: In November 2008, the parties signed an employment agreement providing that Relator was to serve as the director of the school for the 2008-09 school year. The title of the agreement states the dates July 01/2008-June 30/2009. "The first sentence of the agreement lists the administrative positions to which the agreement applies and states, "This is a general at will agreement."(Ellis vs. BlueSky, 2010). Yet the agreement provides that "[p]ositions will automatically renew for one year after one year of service unless specific actions are taken by the board before April 15th of each year" (Ellis vs. BlueSky, 2010). It defines the work year as 220 days from July 1 to June 30, and provides for proration in terms of a new hire within the financial year.…

    • 769 Words
    • 4 Pages
    Good Essays
  • Better Essays

    Memo

    • 1081 Words
    • 5 Pages

    Doyle Contractors has clearly stated the intent not to honor its contractual obligation before the time for performance. Because of this decision Ms. Woodside has an immediate right to commence a lawsuit. What this means is that although the time for the contract is not due, Ms. Woodside does not have to wait until after April 1st 2008 to sue for breach of contract under the contract term where there has been an anticipatory repudiation. (Spagnola, Ch.10)…

    • 1081 Words
    • 5 Pages
    Better Essays
  • Good Essays

    The United Mine Workers went on strike in hope of receiving better wages and a shorter workday. Attorney General Palmer got a court order that told the strikers to return to work. Lewis formally declared the strike over, but it continued for another month until Wilson appointed an arbitrator to decide the remaining issues. The Mine Workers received a 27 percent pay increase, but the same hours.…

    • 382 Words
    • 2 Pages
    Good Essays
  • Satisfactory Essays

    Annotated Bibliography

    • 680 Words
    • 3 Pages

    Assaf, S.A. and Al-Hejji, S. (2006) Causes of delay in large construction projects. International Journal of Project Management, 24(4), 349-57.…

    • 680 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Construction of towers were already behind the schedule; HQ reluctant to terminate the contract since the former company did a great deal of work on the construction…

    • 346 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    Case study

    • 1399 Words
    • 6 Pages

    A company called Abbott Industries submitted an artist's sketch for the ALFA evaluation team to picture what the landscaping would look like. Abbott was selected with a bid of 1.75billion, substantially lower than any other submission. Abbott then prepared a detailed landscaping plan based on existing drawings of the site provided in the tender. Abbott met with the ALFA senior executives to agree project start date, access and security of plant and equipment, and a fixed price contract. A contract was duly signed.…

    • 1399 Words
    • 6 Pages
    Powerful Essays
  • Powerful Essays

    7. How much was the cost of the project and when will be its duration?…

    • 1422 Words
    • 6 Pages
    Powerful Essays
  • Good Essays

    Fitzberg Tire Company

    • 796 Words
    • 4 Pages

    The Fitzburg Tire Company's construction manager, Max Bierman, has been working on a plant in Cuernavaca, Mexico. This plant is Bierman's first assignment outside the U.S. and it is not going according to his expectations. After merely three months, the project is running behind schedule and overriding its forecasted budget. The occurring…

    • 796 Words
    • 4 Pages
    Good Essays