Corwin Corporation Analysis
TABLE OF CONTENTS

EXECUTIVE SUMMARY 2 INTRODUCTION 3 CASE ANALYSIS 4 1. Project Selection 4 1.1 Poor Project Selection 4 1.2 Proposal Preparation 5 1.3 Contract Negotiation 5 1.4 Risk Management Ignored 6 1.5 Project Kickoff Meeting 6 1.6 Change Management 7 2 Lack of Management Support 8 2.1 Organisational Structure and Culture 8 3 Poor Communication 9 CONCLUSIONS 10 RECOMMENDATIONS 10 REFERENCES 11

EXECUTIVE SUMMARY

The purpose of this of document is to analyze the factors that led to the Corwin’s project failure. Corwin Corporation’s relationship with a good customer, Peters Company was strained because of Corwin’s failure to follow their management policies. A fixed-price contract was signed without proper risk analysis, the was no evidence of a project plan and the situation was made worse by the lack of support from management. This report discusses the failures in project selection, lack of executive support and communication breakdown, all of which lead to the project being terminated by the client.

INTRODUCTION

Corwin Corporation accepted a project which was outside their scope of work from Peters Company to develop a specialty product. They accepted the assignment based on a rough draft and without analyzing the risks and thus leading to the project being later terminated by Peters Company and jeopardizing their long-standing good relationship with the client. The project started before the contract was signed. Corwin’s failure could be attributed to a number of errors that were made on accepting this assignment. A number of important factors like the management policy, were completely ignored.
Corwin agreed on a fixed-price 5-year contract based on a rough draft, no proper analysis was done and the scope was unclear. This meant that Corwin would be responsible for any cost overruns incurred. It is never advisable to accept a fixed-price contract without determining the client’s needs and whether



References: James P. Clements & Jack Gido. 2007. Effective Project Management. 5th Edition. South-Western: Cengage Learning. Harold Kerzner, PHD. Project Management: A Systems Approach to Planning, Scheduling, and Controlling. Seventh Edition. USA: John Wiley & Sons Inc. PMBOK® Guide . 2008. A Guide to the Project Management Body of Knowledge. Fourth Edition. USA: Project Management Institute.

You May Also Find These Documents Helpful

  • Good Essays

    Aren’t We Done Yet?

    • 675 Words
    • 3 Pages

    LabCo has entered into a contract with a customer, Halibut, to build a six-axis laser cutting machine that will be used by Halibut to cut airplane wings for a new fighter jet that will be sold by Halibut to a large government buyer. The contract entered into was for a fixed price and requires detailed and involved performance specifications. Upon entering into the contract, LabCo realized that this was a unique arrangement that required a great deal of customer specification in order to meet required performance standards. However, LabCo also…

    • 675 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    Burke, R. (2006). Project Management - Planning and Control Techniques (5th ed.). www.burkepublsihing.com: Burke Publishing.…

    • 13536 Words
    • 144 Pages
    Powerful Essays
  • Powerful Essays

    References: Project Management Institute. (2008). A guide to the project management body of knowledge: PMBOK guide (4th ed.). Newton Square, PA: Author. ISBN: 9781933890517.…

    • 13779 Words
    • 56 Pages
    Powerful Essays
  • Satisfactory Essays

    Law 531 Memorandum

    • 981 Words
    • 4 Pages

    This memo is in response to the dispute over the contract between Span Systems and Citizen-Schwarz AG (C-S). Management is taking the necessary steps in resolving the issues C-S is reporting of low quality deliverables and schedule delays. C-S is threatening rescission of their contract and demand immediate transfer of all unfinished codes (University of Phoenix, 2002, Legal Environment of Business: Contract Creation and Management, Law 531). C-S must prove a material breach is occurring and give adequate notice to Span Systems to issue a rescission (Cheeseman, 2010). Span Systems and C-S signed a one-year contract worth $6 million dollars that has five clauses for breach of contract and a project structure clause. This memo will identify what management is doing to avoid legal risks, minimize liabilities, and benefit from opportunities presented to make this contract successful.…

    • 981 Words
    • 4 Pages
    Satisfactory Essays
  • Good Essays

    In this case study presented by Hood (n.d.), Fauquier Gas Company is up against a timeline to supply a new construction project in the works where agricultural land was being developed into residential and commercial use. Fauquier Gas Company is looking for supplier to help with building of 3 ½ miles of new gas pipe that will go online by beginning of September. The manager of supply management Mr. Murphy is having trouble getting any purchasing request for the new pipeline from Mr. Charlie Buck and the specifications from the design team to know what he needs to order. This project is to be complete in the next five months to meet the new gasoline project. The vice-president of operations for Fauquier Gas Company has the management control over the supply organization including Mr. Murphy, construction project manager Clive Byers, design engineer Pat Wilson, and design Superintendent Charlie Buck. Mr. Murphy faced many logistical and supply problems from the very beginning of this project. Lead-time is essential for design team getting all the information on the new pipe to the Mr. Murphy so he can get the much need specification out to the need vendors to supply the correct materials for the upcoming project that need to finish by September. The biggest problem that Mr. Murphy came across was the new specifications for the new pipe were the wall thickness and length was different from previous purchases which could hurt in finding new vendor or seeing if older vendor can meet specifications on the new pipe. Pat Wilson informed Mr. Murphy the reason for the different specifications was the operation of the line would be governed by less stringent specifications and using 57-foot-length pipe versus “random double normal” (40 feet plus or minus 5 feet) would reduce welding costs. The coating for the pipe was also another problem that Mr. Murphy faced as no of team was communicating with each other on how to…

    • 901 Words
    • 4 Pages
    Good Essays
  • Powerful Essays

    Risk Management Plan

    • 2116 Words
    • 9 Pages

    Project Management Institute. (2008). A guide to the project management body of knowledge Retrieved from http://ezproxy.gsu.edu:2048/login?url=http://www.books24x7.com/marc.asp?bookid=29854…

    • 2116 Words
    • 9 Pages
    Powerful Essays
  • Powerful Essays

    Scotts Miracle Gro

    • 2658 Words
    • 11 Pages

    This is an in-depth case analysis of the Scotts’ Miracle-Gro Company (Scotts) alternative decisions regarding what to do with the Scotts’ plant based in Temecula, California. The Scotts Company was founded by Orlando McLean Scott in 1868, and was located in Marysville, Ohio. Scotts started its spreader business with the introduction of drop spreaders in 1930. In 1995 Scotts Miracle-Gro was formed after the merger of Scotts and Miracle-Gro making it the largest company in North America’s lawn and garden industry, and the worlds leading supplier and marketer of consumer lawn and garden care products (Gray & Leiblein, 2008).…

    • 2658 Words
    • 11 Pages
    Powerful Essays
  • Better Essays

    2) Pressure from leadership. Interagency politics and lack of planning resulted in this procurement being somewhat rushed. Current year funds expiring and senior manager eagerness are not appropriate factors to force a contract specialist to consider.…

    • 1374 Words
    • 4 Pages
    Better Essays
  • Good Essays

    References: Larson, E. W., & Gray, C. F. (2011). Project Management (5th ed.). New York, New York: McGraw-Hill Irwin.…

    • 681 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    Orion Shield Project

    • 5525 Words
    • 23 Pages

    Executive Summary The basic concepts of project management calls for proper planning, organization and the management of a variety of resources in order to successfully achieve a certain goal. One of the most important objectives of project management is the ability to deliver a product or service within a certain time constraint or “on time” as well as being fiduciary responsible or “within budget.” Thus, it can be seen that good project management makes efficient use of time, money, personnel, materials and supplies, and methods of communication in order to successfully complete a project. Unfortunately, these basic methods of project management were not…

    • 5525 Words
    • 23 Pages
    Powerful Essays
  • Powerful Essays

    Chunnel Project

    • 9442 Words
    • 38 Pages

    This case study was originally prepared as part of Project Management Applications, the capstone course of the Master of Science in Project Management in the Department of Management Science at The George Washington University, by the graduating students listed above with the supervision of Professor Anbari.…

    • 9442 Words
    • 38 Pages
    Powerful Essays
  • Best Essays

    Case Study Woody 2000

    • 2614 Words
    • 11 Pages

    In 1989, Due to a mini-boom in commercial construction, Bruce Sharpe, the company’s VP Sales and Estimating persuaded directors to expand their manufacturing business. There were two options for the company to go and there were either stay in the premises and expand or relocate to completely new and more modern facilities. Due to various personal views on this issue and polarization of opinions, Ron Carpenter, also called “Woody”, organized a meeting of directors and key personnel to come to a resolution regarding this matter. Based on the meeting, project concept was settled that the company will remain at the existing property but will expand the current facility by 25%. The premises will be modernized with new equipment, software and hardware and the directors’ premises will be renovated. The budget available for the changes was set at $17 million and a target date of 18 months.…

    • 2614 Words
    • 11 Pages
    Best Essays
  • Better Essays

    ERP implementation

    • 1476 Words
    • 5 Pages

    Risk that associated with ERP implementation and measures that can be taken to fix these risks.…

    • 1476 Words
    • 5 Pages
    Better Essays
  • Satisfactory Essays

    3) Should Pat Ray have been given the freedom to visit laboratory personnel at any time? Should…

    • 279 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    Project management is defined as professional services involving the establishment and monitoring of overall implementation strategy on a project from the design stage through to construction and commissioning stages. Hence an effective project manager must understand the client’s business, the purpose and nature of the project and it’s impact on the client’s business in addition to understanding the business of managing projects. Fulfillment of this objective requires both vision and skill on the part of the Project Manager. Most project managers in Nigeria do not fully understand and appreciate the magnitude of this role, hence leading to project abandonment in most cases.…

    • 3333 Words
    • 14 Pages
    Powerful Essays

Related Topics