Preview

Book Report

Good Essays
Open Document
Open Document
683 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Book Report
1. Provide the definitions of critical path and critical chain. How do they differ?

Critical path and critical chain are both schedule network analysis techniques.

Critical path is the one that determines the shortest time to complete a project, which assumes low uncertainty and does not consider resource dependencies.

Critical chain is a modified or refined technique about critical path; it involves the deterministic and probabilistic approaches to analyze the project schedule, which is more realistic and practical than critical path.

Differences between critical path and critical chain:
 Critical path is based on deterministic task duration, while critical chain involves the deterministic and probabilistic approaches;

 Critical path does not consider resource dependencies, while critical chain is based on resource constraints;

 Critical path does use buffer time efficiently, while critical chain uses optimum buffer time to reduce the risk of schedule;

 Critical path is less focused on non critical tasks that may cause risk, while critical chain controls risks more efficiently by considering more tasks and applying optimum buffer time.

2. What are inventory buffers analogous to in project management? List various kinds of buffers used to manage projects and describe where each of them should be located.

Inventory buffers are analogous to, in project management, time buffers.

Types of buffers used to manage projects are as below.
 Resource buffers (RB): buffers that is located along with the critical path and specifically ahead of a task involving important resources. The purpose of Resource buffers is to make sure that the involved resources such as materials, machinery, and labor resources are available for the task, before the task is launching or during the process of the task.

 Project buffers (PB): buffers that are amount of times located at the end of a project or, say, at the end of a critical path. It is made

You May Also Find These Documents Helpful

  • Good Essays

    -2- 6. The critical path of a project network is the: a. shortest time path through the network. b. path with the fewest activities. c. path with the most activities. d. longest time path throught the network.…

    • 882 Words
    • 8 Pages
    Good Essays
  • Satisfactory Essays

    The following data were obtained from a project to build a pressure vessel: Activity Duration Predecessors A 6 weeks --- B 6 weeks --- C 5 weeks B D 4 weeks A, C E 5 weeks B F 7 weeks D, E, G G 4 weeks B H 8 weeks F I 5 weeks G J 3 week I Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) Calculate the scheduled completion time. (5 points) b) Identify the critical path (6 points) c)…

    • 556 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Huffman Trucking Benefits

    • 278 Words
    • 2 Pages

    The Critical Path Method will indicate the longest path of planned to the end of the project. It is a very good tool to use because it will give the Project Manager a good idea of what tasks that must be completed on time in order for the project to continue smoothly. This method is commonly used in the development of new…

    • 278 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    First Cars Ltd

    • 1031 Words
    • 5 Pages

    Critical path analysis is a method that is used to plan out the many activities involved in a project to be able to find the most efficient way of complete it and how to complete it on time.…

    • 1031 Words
    • 5 Pages
    Good Essays
  • Satisfactory Essays

    I a. Construct a network for the project. [pic] Slack or Float = LF – EF or LST – EST Activities on the critical path have zero slack/float. b. Calculate the scheduled completion time and identify the critical path.…

    • 562 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    mis 302

    • 1114 Words
    • 5 Pages

    The Critical Path is the Shortest Time in which the Project Can Be Completed. Any delay in Critical Path activities delays the project. Critical Path Activities have no slack time Variability in Activity Times: CPM assumes we know a fixed time estimate for each activity and there is no variability in activity times PERT uses a Probability Distribution for Activity Times to allow for Variability.…

    • 1114 Words
    • 5 Pages
    Good Essays
  • Satisfactory Essays

    AIB Problem

    • 565 Words
    • 3 Pages

    Step 2: Answer the following questions: (15 points total) a) Calculate the scheduled completion time. (5 points) Answer: 30 days b) Identify the critical path (6 points) Answer: B, C, D, F, H c)…

    • 565 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Red Zuma Project

    • 402 Words
    • 2 Pages

    Market Analysis, Product Design, Product Design Selection, Detailed Project Design, Build Prototypes, Field Test Prototypes, Finalized Product Design, Final Manufacturing Process, Order Components, Order Production Equipment, Install Production Equipment, and Celebrate.…

    • 402 Words
    • 2 Pages
    Good Essays
  • Powerful Essays

    Dragonfly case study

    • 1041 Words
    • 5 Pages

    4. The critical path for the project is found by calculating slack as per CPM as shown in the table below. The activities marked in green forms the critical path, I e.,…

    • 1041 Words
    • 5 Pages
    Powerful Essays
  • Satisfactory Essays

    2. What activities lie on the critical path? The critical path is highlighted in red, the activities in order from commencement are as follows;…

    • 264 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    A&D High Tech (A)

    • 613 Words
    • 3 Pages

    3. What is (are) the critical path(s) in the project? What is the level of risk in completing tasks on the critical path(s)? Explain.…

    • 613 Words
    • 3 Pages
    Good Essays
  • Good Essays

    What is a critical path, and why is it important to project managers? How do you…

    • 702 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    2- What is the critical path and how long is the project expected to take?…

    • 294 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    A&D HIGH TECH

    • 263 Words
    • 2 Pages

    What is the critical path in the project? How would you assess the level of risk in the project?…

    • 263 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    Process Mapping

    • 992 Words
    • 4 Pages

    - Prioritize key things that need to be done, elements in critical path, customer delivery preference…

    • 992 Words
    • 4 Pages
    Powerful Essays