Preview

02 Network Planning tutorial

Satisfactory Essays
Open Document
Open Document
590 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
02 Network Planning tutorial
1. Construct the CPM network described by the following set of activities, compute the length of each path in the network, and indicate the critical path. Activity
Time (weeks)
1 2
5
1 3
4
2 4
3
3 4
6

2. Construct the CPM network described by the following set of activities, compute the length of each path in the network, and indicate the critical path. Activity
Time (weeks)
1 2
3
1 3
7
2 4
2
3 4
5
3 5
6
4 6
1
5 6
4

3. Construct the CPM network described by the following set of activities, compute the length of each path in the network, and indicate the critical path. Activity
Time (months)
1 2
4
1 3
7
2 4
8
2 5
3
3 5
9
4 5
5
4 6
2
5 6
6
3 6
5

4. Given the following network with activity times in months, determine the earliest and latest activity times and slack for each activity. Indicate the critical path and the project duration.

5. In one of the little-known battles of the Civil War, General Tecumseh Beauregard lost the Third Battle of Bull Run because his preparations were not complete when the enemy attacked. If the critical path method had been available, the general could have planned better. Suppose that the following planning network with activity times in days had been available. Determine the earliest and latest activity times, and activity slack for the network. Indicate the critical path and the time between the general’s receipt of battle orders and the onset of battle.

6. A group of developers is building a new shopping center. A consultant for the developers has constructed the following project network and assigned activity times in weeks. Determine the earliest and latest activity times, activity slack, critical path, and duration for the project.

7. A farm owner is going to erect a maintenance building with a connecting electrical generator and water tank. The activities, activity descriptions and estimated durations are given in the following table. Construct the network for this project, identify the

You May Also Find These Documents Helpful

  • Satisfactory Essays

    3. Now choose one of these strategies and perform the necessary calculation. Explain in complete sentences why you have chosen this strategy.…

    • 261 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    The following data were obtained from a project to build a pressure vessel: Activity Duration Predecessors A 6 weeks --- B 6 weeks --- C 5 weeks B D 4 weeks A, C E 5 weeks B F 7 weeks D, E, G G 4 weeks B H 8 weeks F I 5 weeks G J 3 week I Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) Calculate the scheduled completion time. (5 points) b) Identify the critical path (6 points) c)…

    • 556 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Documents NETW240 Wk4 Lab

    • 1983 Words
    • 10 Pages

    In this module you will be working on the following equipment to carry out the steps defined in each exercise.…

    • 1983 Words
    • 10 Pages
    Satisfactory Essays
  • Good Essays

    1) (2 point) In this exercise, you create the routing for your finished product, Rocker. Note the shown below. In step #5, the value of 1 is entered into the From Lot Size field.…

    • 711 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    QAT1 Task 4

    • 501 Words
    • 7 Pages

    E 7.5 14 12.5 19 6.5 F 7 7 17 17 0 CRITICAL G 17 17 23.5 23.5 0 CRITICAL H 18.5 19 29.5 30 0.5 I 23.5 23.5 30 30 0 CRITICAL J 30 30 33.5 33.5 0 CRITICAL a. Duration of project: 33.5 weeks b. Slack for task A: 6.5 weeks c. Slack for task H: 0.5 weeks d. Task F scheduled start: week 7 e. Task I scheduled completion: week 30 4.…

    • 501 Words
    • 7 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Organic Chem

    • 521 Words
    • 3 Pages

    c. Mark points on the energy diagram corresponding to each carbocation in your mechanisms. See the blue # above.…

    • 521 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    5. [3] Ten processes share a critical section implemented by using a semaphore x. Nine…

    • 299 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Comp 122 Week 1 Ilab

    • 662 Words
    • 3 Pages

    3. Design an algorithm in pseudocode to solve the problem. Make sure to include steps to get each input and to report each output.…

    • 662 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    cmis 102 HW 2

    • 748 Words
    • 6 Pages

    Using the Hierarchical Design, I am creating a flow chart or blueprint of how basically this program will work:…

    • 748 Words
    • 6 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Rccoleman

    • 850 Words
    • 4 Pages

    3. Using the expected activity times as the normal times and the following crashing information, determine the activity crashing decisions and revised activity schedule for the warehouse expansion project:…

    • 850 Words
    • 4 Pages
    Satisfactory Essays
  • Satisfactory Essays

    C) Again, an Euler circuit would be possible. A small number of vertices to visit would make finding a path without retracing possible.…

    • 473 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Activity 5

    • 937 Words
    • 4 Pages

    Step 2: Calculate a summary route on R3 to reach LANs on R1 and R2.…

    • 937 Words
    • 4 Pages
    Satisfactory Essays
  • Good Essays

    A&D High Tech (A)

    • 613 Words
    • 3 Pages

    3. What is (are) the critical path(s) in the project? What is the level of risk in completing tasks on the critical path(s)? Explain.…

    • 613 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    Os Deadlocks

    • 450 Words
    • 2 Pages

    Compute the Need Matrix. Is the system safe? If so, show the order in which all processes can complete. If the system is not safe, explain.…

    • 450 Words
    • 2 Pages
    Satisfactory Essays
  • Better Essays

    coaiso

    • 4410 Words
    • 34 Pages

    given and find the answers. Finding the rule followed by the machine is the key task. Once you…

    • 4410 Words
    • 34 Pages
    Better Essays