Assignment 2
Haeryip Sihombing

BANK SOAL – BMFP 4542 (TEST -1)
1. Identify and briefly describe the five commonly traded organizational currencies.
• • • • • Task-related; the ability to contribute to others accomplishing their work, Position-related; the ability to enhance others' positions within their organization, Inspiration-related; the ability to enhance people's desire to make a difference and add meaning to their lives, Relationship-related; the ability to form relationships that transcend normal professional boundaries and extend into friendship, Personal-related; the extent to which one can help others feel a sense of importance and personal worth.

2. Identify and compare the old-fashioned view of managing projects and the new perspective of managing projects.
The old-fashioned view of managing projects emphasized directing and controlling subordinates; the new perspective emphasizes managing project stakeholders and anticipating change as the most important jobs.

3. Under what conditions would the top-down approach to estimating project times and costs be the best choice?
In the early stages of a project to help develop the initial plan, in making strategic decisions, in projects of high uncertainty, in small internal projects, or in projects with an unstable scope.

4. Under what conditions would the bottom-up approach to estimating project times and costs be the best choice?
When low cost, efficient estimates are needed, when time and cost are important, when working on a fixed price contract, or when the customer wants details.

5. In the network computation process what is a forward pass and what three things does it determine?
Starting with the first activity, each path is traced forward through the network, adding times until the end of the project. This determines 1. how soon each activity can start, 2. how soon each activity can finish, and 3. how soon the entire project can be completed.

6. What is a risk profile and what benefits

You May Also Find These Documents Helpful

  • Better Essays

    1. Calculate the total indirect cost and determine a indirect cost for the appropriate period.…

    • 1854 Words
    • 8 Pages
    Better Essays
  • Satisfactory Essays

    Nt1310 Unit 4

    • 555 Words
    • 3 Pages

    a. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?…

    • 555 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    8. Two companies come together to take on a project that has an explicit time cycle and ending point. The most efficient form of acquisition of this project is…

    • 250 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    Project Costing wk4TeamB

    • 1051 Words
    • 6 Pages

    Cost estimates are the one that could have a high risk over the project and it is the one…

    • 1051 Words
    • 6 Pages
    Powerful Essays
  • Satisfactory Essays

    Mr. Doe

    • 686 Words
    • 3 Pages

    * 3. Identify a preliminary set of tangible and intangible costs you think would occur for this project and the system it describes. What intangible benefits do you anticipate for the system?…

    • 686 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Ridoran Outline

    • 389 Words
    • 3 Pages

    a) Specify tradeoffs between cost, schedule, and performance. A fast and inexpensive solution may not adequately address performance requirements.…

    • 389 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Larson, E. W. & Gray, C. F. (2006). Project Management: The Managerial Process. USA: McGraw- Hill International.…

    • 414 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    One of the most important factors to the success of a project is how well the project is estimated, as well as how overall costs are managed during the execution phase by the project manager. Project costs and estimates are vital to the success of any organization to remain competitive in the market. Cost estimating for organizations rely heavily on resources that can sometimes be difficult to obtain. Forecasting and utilizing historical return costs are just a couple of ways that organizations rely on estimating. Experienced planners are often a sought trade within the market; this paper will discuss some often used project cost estimating techniques.…

    • 746 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Week 4 Knowledge Check

    • 355 Words
    • 2 Pages

    8.Two companies come together to take on a project that has an explicit time cycle and ending point. The most efficient form of acquisition of this project is…

    • 355 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Week Dqs

    • 274 Words
    • 2 Pages

    Accurate estimates are critical to effective project management because having accurate time and costs estimates helps ensure the project is a success. Project control is dependent on accuracy of estimates, time and cost, estimates are major inputs to project planning. Estimates are used to support good decisions to determine project duration and cost. Used to develop time phased budgets and estimating helps reduce error. Project managers can take steps to improve the accuracy of estimating projects by using techniques to scope, constrain and plan the projects conditions, this will help reduce risks, and increase the project’s success.…

    • 274 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    Time, which could cost you the most, on these types of projects are needed to determine how much it will cost, for the company and project managers. You will need to know how much time will be needed to complete the job, so the management can make the decision about how plausible it will be to go further in the plan.…

    • 1059 Words
    • 5 Pages
    Powerful Essays
  • Satisfactory Essays

    Depreciation and Cost

    • 549 Words
    • 3 Pages

    3. I prefer the system proposed by the consultant because it is the most detailed, therefore will produce more accurate costs.…

    • 549 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    Project managers are ultimately responsible for making projects happen. Carrying out this task requires a broad set of skills. In addition to exercising their knowledge of project management best practices, project managers also perform a variety of roles during a project 's life cycle. They serve as business liaisons, budget managers, communicators, customer relations managers, the project team 's cheerleaders, facilitators, negotiators, risk managers, change agents, motivators, presenters, planners, task trackers, problem solvers and implementers (Guzman, 2010).…

    • 2266 Words
    • 6 Pages
    Powerful Essays
  • Powerful Essays

    Classification of the project—e.g., large/small, platform/incremental, complex/ typical * Analysis of information gathered * Recommendations * Lessons learned * An appendix with backup information to support recommendations. 2. Why is it difficult to perform a truly independent, objective review?In most cases those performing the review have some previous knowledge of the project, which presents opportunities for bias. Sometimes the review team, or facilitator, is perceived as a jury, but even jury members come with built-in biases. For example, internal politics have been known to enter into decisions concerning closure of a project. The simple point is that every attempt should be made to keep the review independent and objective. If the review of projects is a regular procedure for all projects, the negative stigma of audits is minimized. 3. Why should you separate performance…

    • 875 Words
    • 4 Pages
    Powerful Essays
  • Good Essays

    Calculating each activity provides a useful control tool for the operations manager. The manager will be able to see whether the project is up to schedule by checking the actual completion times of activities against the network.…

    • 475 Words
    • 2 Pages
    Good Essays

Related Topics